home *** CD-ROM | disk | FTP | other *** search
/ Boot Disc 8 / boot-disc-1997-04.iso / PDA_Soft / Psion / misc / Plan / Plan1.txt < prev    next >
Text File  |  1996-07-07  |  29KB  |  698 lines

  1.                 Plan
  2.                                                                     
  3.                  User Guide
  4.                                                                     
  5.                 Version 4.1
  6.  
  7. Copyright  Andy Clarkson 1995,1996
  8. All rights reserved.
  9.  
  10. The  information within this manual and the associated software  are
  11. subject to change without notice.
  12.  
  13. Some  of  the  names used within this manual and  displayed  by  the
  14. software  are registered trademarks. Such names are acknowledged  as
  15. trademarks even though they have not been marked with the  symbol.
  16.  
  17. CONTENTS
  18.  
  19. 1. INTRODUCTION
  20.     1.1 About this manual
  21.     1.2 What is Plan?
  22.     1.3 Installation
  23.         1.3.1 Installation of Plan from a ready to run SSD
  24.         1.3.2 Manual installation of Plan
  25.  
  26. 2. PROJECT PLANNING
  27.     2.1 Fundamental concepts
  28.     2.2 Example
  29.     2.3 Calculation of task start dates
  30.  
  31. 3. FAST START TUTORIAL
  32.     3.1 Creating a new plan
  33.     3.2 Creating a new resource
  34.     3.3 Creating tasks
  35.     3.4 Setting dependencies
  36.     3.5 Summary tasks
  37.     3.6 Updating a task
  38.     3.7 Tracking work done
  39.     3.8 Reviewing a task when it is underway
  40.     3.9 Task end/work/rate calculation
  41.     3.10 Views
  42.     3.11 Example Plan
  43.  
  44. 4. KEY FEATURES
  45.  
  46. 5. PLAN AND RESOURCE FILES
  47.  
  48. 6. VIEWS
  49.     6.1 Task view
  50.     6.2 Task list view
  51.     6.3 Gantt chart
  52.     6.4 PERT chart
  53.         6.4.1 Appearance of the PERT chart
  54.         6.4.2 Positioning tasks in the PERT chart
  55.         6.4.3 Moving around the PERT chart
  56.     6.5 Resource usage view
  57.         6.5.1 Resource work hours
  58.         6.5.2 Resource usage histogram
  59.         6.5.3 Over-allocated resources
  60.     6.6 Holiday view
  61.  
  62. 7. TASKS
  63.     7.1 Standard Tasks
  64.     7.2 Summary Tasks
  65.     7.3 Deleting tasks
  66.     7.4 Masking tasks
  67.  
  68. 8. DEPENDENCIES
  69.  
  70. 9. COST AND USER DATA
  71.  
  72. 10. TASK CALCULATION AND TRACKING
  73.     10.1 Calculation (end/work/rate)
  74.     10.2 Tracking work done
  75.     10.3 Reviewing a task when it is underway
  76.  
  77. 11. MEMOS
  78.  
  79. 12. RESOURCES
  80.  
  81. 13. PREFERENCES
  82.  
  83. 14. PRINTING
  84.  
  85. 15. MODULES
  86.     15.1 Microsoft Project MPX module
  87.     15.2 Postscript module
  88.     15.3 Agenda module
  89.  
  90. 16. COMMAND SUMMARY
  91.  
  92. 1. INTRODUCTION
  93.  
  94. 1.1 About this manual
  95.  
  96. This manual describes how to use Plan for the Psion 3a.
  97.  
  98. A version of  this manual  which includes  screenshots is  available
  99. from my homepage (http://ourworld.compuserve.com/homepages/andyc).
  100.  
  101. The  installation  instructions within this section  of  the  manual
  102. describe how to install Plan.
  103.  
  104. The section "Project planning" describes key concepts which are used
  105. throughout  this manual and should be read before the  rest  of  the
  106. manual.  Plan is easy to use, provided that the fundamental concepts
  107. are  understood. This manual should be sufficient in  order  to  use
  108. Plan, however if you are unfamiliar with project planning in general
  109. then  you  may wish to read one of the many books available  on  the
  110. subject.
  111.  
  112. The  "Fast  start tutorial" section describes the main  features  of
  113. Plan  and provides a quick method of getting up to speed with  Plan.
  114. The  rest of the manual contains detailed information on all of  the
  115. features of Plan.
  116.  
  117. On-line  help  is available from the help key within  Plan  provided
  118. that the on-line help file has been installed.
  119.  
  120. 1.2 What is Plan?
  121.  
  122. Plan  is  a  project planning tool for the Psion 3a.  It  allows  an
  123. initial  project  plan to be created and refined  and  subsequently,
  124. when  the  project  is  underway, provides facilities  for  tracking
  125. progress.
  126.  
  127. A  project  consists of a set of resources, (individuals or  groups)
  128. who  are  assigned to specific tasks within the project. The project
  129. is  split into a number of separate tasks. Each task has a start and
  130. end  date,  an  amount of work, and a number of assigned  resources.
  131. Dependencies  may  be set between tasks, indicating  that  one  task
  132. cannot  start  until another finishes. In this way if  one  task  is
  133. updated  within  Plan, any tasks dependent upon  the  task  will  be
  134. recalculated automatically.
  135.  
  136. Plan  may be used as a stand-alone project planning tool or  may  be
  137. used  in  conjunction with PC based project planning tools  such  as
  138. Microsoft  Project. When used with Microsoft Project, Plan  provides
  139. an  ideal  means of transporting project plans out of the office.  A
  140. project  plan may be transferred from Microsoft Project on a  PC  to
  141. Plan on the Psion and readily updated "on the move". The project may
  142. subsequently  be  transferred back to the  PC  upon  return  to  the
  143. office.
  144.  
  145. 1.3 Installation
  146.  
  147. Plan may be supplied either ready to run on a Psion Solid State Disk
  148. (SSD)  or  may  need  to be installed from the  distribution  media,
  149. (usually a 3.5" MSDOS floppy disk).
  150.  
  151. Before  installing Plan ensure that any previous version of Plan  or
  152. Plan Deluxe has been backed up and removed from the Psion.
  153.  
  154. 1.3.1 Installation of Plan from a ready to run SSD
  155.  
  156. If  Plan is supplied ready to run on an SSD then insert the SSD into
  157. one  of  the  SSD drives on the Psion. From the Psion system  screen
  158. select  the  "Install" menu option from the "Apps" menu. Change  the
  159. displayed  disk item to refer to the drive which contains  the  Plan
  160. SSD and select the file named "Plan.opa". Press enter to install the
  161. Plan icon onto the Psion system screen.
  162.  
  163. 1.3.2 Manual installation of Plan
  164.  
  165. If  Plan  is  provided on a floppy disk or you want to install  Plan
  166. onto another Psion drive, such as an SSD, then proceed as follows...
  167.  
  168. A  typical installation of Plan on the Psion 3a would consist of the
  169. following files:
  170.  
  171.      M:\APP\PLAN.OPA
  172.      M:\APP\PLAN\PLAN.MSG
  173.  
  174.      M:\APP\PLAN\PLAN.HLP     (optional)
  175.      M:\APP\PLAN\PLAN.TTL     (optional)
  176.      M:\APP\PLAN\AGN.OPO      (optional)
  177.      M:\APP\PLAN\MPX.OPO      (optional)
  178.      M:\APP\PLAN\PS.OPO       (optional)
  179.      M:\OPD\PLAN.REG          (optional)
  180.  
  181.      M:\PLN\EXAMPLE.PLN       (optional)
  182.      M:\PLN\EXAMPLE.RES       (optional)
  183.  
  184. The  above  example shows Plan installed on the internal drive  (M).
  185. Plan may also be installed on a RAM or FLASH SSD in drive A or B.
  186.  
  187. Plan  requires  between 90K and 150K of disk space for  installation
  188. depending  upon whether the optional files are installed. A  minimum
  189. of  35K  of  run-time  memory is required in order  to  start  Plan,
  190. additional  memory will be required depending upon  the  size  of  a
  191. plan.
  192.  
  193. Start  the  installation by copying the Plan main  application  file
  194. PLAN.OPA into a directory called \APP on any drive and install  from
  195. the system screen as described in section 1.3.1.
  196.  
  197. If  you  are installing Plan from a PC using PsiWin and the  message
  198. "Failed  to convert file" is displayed when dragging files from  the
  199. PC to the Psion, then you will need to turn off automatic conversion
  200. of  files. This may be done by selecting the "Conversions" menu item
  201. from  the "Setup" menu in PsiWin. Ensure that "Allow convert on Drag
  202. & Drop between Computers" is turned off.
  203.  
  204. Create  a  directory called PLAN below the APP directory  where  the
  205. PLAN.OPA  file has been installed.  Copy the Plan message file  into
  206. the \APP\PLAN directory:
  207.  
  208.      PLAN.MSG
  209.  
  210. The   remaining  files  which  may  be  installed  provide  optional
  211. facilites. These files may be omitted from the installation  if  you
  212. are short of disk space.
  213.  
  214. If installing  Plan via a Mac and you get the  message "Incompatible
  215. message file" when first starting  Plan then this indicates that the
  216. PLAN.MSG file  has been corrupted.  The cause of  this is often that
  217. the file has been  treated as a text file rather  than a binary file
  218. when extracting  it from the supplied  ZIP file.  The solution is to
  219. ensure that a file with  extension .MSG is extracted  with a type of
  220. "BINA" (binary file) by setting the preferences appropriately.
  221.  
  222. If  on-line  help is required then also copy the on-line  help  file
  223. into the \APP\PLAN directory:
  224.  
  225.      PLAN.HLP
  226.  
  227. If a registration file, PLAN.REG, has been supplied copy this to the
  228. \OPD directory, otherwise you will need to enter a registration code
  229. using the "Registration" menu option on the "Special" menu when  you
  230. start Plan.
  231.  
  232. The PLAN.TTL file provides an optional title screen when Plan starts
  233. and may be copied into the \APP\PLAN directory.
  234.  
  235. If  any  of  the optional plan modules are required then  they  also
  236. should  be  copied  into  the  \APP\PLAN  directory.  The  currently
  237. available  Plan  modules are AGN.OPO, PS.OPO and  MPX.OPO.  See  the
  238. "Modules"  section of this manual for further details  on  what  the
  239. various Plan modules are for.
  240.  
  241. The  plan  and resource files used by Plan should be kept in  a  top
  242. level  directory  called  \PLN on either the  internal  disk  or  an
  243. external RAM disk. An example project plan, EXAMPLE.PLN, along  with
  244. a  resource file, EXAMPLE.RES, are provided which may optionally  be
  245. installed into the \PLN directory.
  246.  
  247. This  software is provided as is, without any warranty of any  kind.
  248. The  author and distributor shall not be liable for any loss of data
  249. or damage arising from the use of this software.
  250.  
  251. 1.4 SHAREWARE REGISTRATION
  252.  
  253. Plan  is shareware, which means that if you continue to use  it  you
  254. should  register  with  the  author.  The  software  may  be  freely
  255. distributed  provided  all  files in the  package  are  included.  A
  256. maximum  of  10 tasks may be entered until the program is registered
  257. by entering a special code via the register menu option.
  258.  
  259. To register send a 15 UK pounds cheque to:
  260.  
  261.  Mr. A. Clarkson,
  262.  3 Ashmead Drive,
  263.  Hardwick,
  264.  Cambridgeshire.
  265.  CB3 7XT.
  266.  U.K.
  267.  
  268. When registering please state the version of the program, (which  is
  269. 4.1), and where you obtained the copy. This allows me to check  that
  270. you are using the latest version.
  271.  
  272. In  return  for  the registration you will receive a  password  code
  273. which  may be entered into Plan. This will remove the 10 task  limit
  274. which  applies to the unregistered version, enabling up to 200 tasks
  275. to  be entered. If you have an email address quote this in order  to
  276. receive the registration code via email more quickly.
  277.  
  278. For members of Compuserve, Plan may be registered electronically via
  279. the  SWREG  facility (Enter "GO SWREG" and select the file  with  ID
  280. 6310).  The  charge  is  US$25 which will be added  to  your  normal
  281. Compuserve bill.
  282.  
  283. For  users outside the UK the following methods of payment can  also
  284. be accepted:
  285.  
  286.     Payment in UK pounds            15 UK pounds
  287.     (cash, cheque, eurocheque
  288.     or money order)
  289.  
  290.     Payment via cash in local    equivalent of 17 UK pounds
  291.     currency (non-UK pounds)        (US$25)
  292.  
  293.     Payment via a cheque in        equivalent of  19  UK  pounds
  294.     local currency (non-UK pounds)    (US$30)
  295.  
  296. The  additional charges for non-UK currency is to cover exchange and
  297. bank charges.
  298.  
  299. For  any  further  information  I can  be  contacted  via  email  at
  300. 100661.2440@compuserve.com
  301.  
  302. 2. PROJECT PLANNING
  303.  
  304. 2.1 Fundamental concepts
  305.  
  306. Plan  allows  a project plan to be constructed from individual  task
  307. components.  Task  and  resource  details  are  entered   into   the
  308. application  along with dependencies between tasks. The  application
  309. will then calculate the schedule for each task and the project as  a
  310. whole.
  311.  
  312. Each task within a project plan has the following key values:
  313.  
  314.  - start  constraints (given by a specified  start  date  and/or
  315.    dependencies upon earlier tasks)
  316.  - the amount of work required to complete the task
  317.  - a number of assigned resources working at a given rate
  318.  - end date and time
  319.  
  320. Usually three of the above values are entered, with the other  value
  321. being calculated by Plan. For example:
  322.  
  323.  - End.  A  start  date  and time may be specified  (usually  in
  324.    relation to the end of an earlier task) along with an amount of work
  325.    and details about assigned resources. Plan will then calculate the
  326.    end date and time for the task. This is the most common calculation
  327.    method.
  328.  
  329.  - Work.  Given  a  start and end date and  time,  and  assigned
  330.    resources, Plan will calculate the work. This could be used where a
  331.    task has been completed, the start and end are known, along with the
  332.    average work rates for each assigned resource, but the total amount
  333.    of work needs to be calculated.
  334.  
  335.  - Rate.  Given  a  start and end date and  time  and  the  work
  336.    required,  Plan  will calculate the average work rates  for  each
  337.    assigned  resource. This could be used in order to calculate  the
  338.    number of people required to complete a task on a given date.
  339.  
  340. A  number of resources may be assigned with given work rates to each
  341. task.  The  resource work hours, holiday information and work  rates
  342. are then taken into consideration when calculating task values, such
  343. as end dates.
  344.  
  345. 2.2 Example
  346.  
  347. Consider a task which is estimated to take two man days to complete,
  348. (one  man  day being the time between the start and end of a  normal
  349. working  day,  set  to  8.0  hours in this  particular  example).  A
  350. resource  is  assigned  to  the task  where  the  resource  has  the
  351. following attributes:
  352.  
  353.  - Works a standard work day, starting at 9:00am, ending at 5:00pm
  354.  - Works a standard week starting on Monday and ending on Friday.
  355.  
  356. The task start day is set to a Monday at 9:00am and the work set  to
  357. two  days.  Plan  calculates the end of the task  to  be  5:00pm  on
  358. Tuesday. Assume now that the resource is only available to  work  on
  359. the  task at a rate of 50% rather than 100%. Plan would now indicate
  360. the  end of the task to be Thursday at 5:00pm. Assume also that  the
  361. resource takes one day holiday on Tuesday. Plan would calculate  the
  362. end  to be Friday at 5:00pm. Suppose that the task is completed  and
  363. actually  finished  at  5:00pm on Wednesday rather  than  5:00pm  on
  364. Friday.  Plan  will allow the end time to be set to the  actual  end
  365. time  and  will  then calculate the work given the  start,  end  and
  366. resource details to be one man day rather than two.
  367.  
  368. Plan works internally down to an accuracy of one second. There is an
  369. option  in  the preference settings for each project which  controls
  370. whether  values are entered and displayed in units of days or  units
  371. of days, hours, minutes and seconds.
  372.  
  373. 2.3 Calculation of task start dates
  374.  
  375. The  start of any task is controlled either by dependencies  defined
  376. on  earlier tasks, a specified start on/after date, or a combination
  377. of the two.
  378.  
  379. Dependencies may be set between tasks so that the start of one  task
  380. depends  upon the end of another. If the first task is  delayed  the
  381. second will also be delayed. Dependencies may be set for a number of
  382. reasons, such as:
  383.  
  384.  - If one task cannot logically start until another task finishes.
  385.    For example, in a software development project the development may
  386.    be dependent upon the requirements phase.
  387.  
  388.  - Resource limitations may impose dependencies, for example  if
  389.    two tasks need to be carried out by one person, and the person works
  390.    on the tasks sequentially, then a dependency should be set between
  391.    the tasks.
  392.  
  393. When  creating a task a start on/after date may be set  to  indicate
  394. either  that the task should start on the specified date  or  cannot
  395. start  before  the given date. If no dependencies have been  defined
  396. then the given date will be used as the start date for the task.  If
  397. the  task  has one or more dependencies upon earlier tasks then  the
  398. latest  date  will  be  used as the task  start  date,  taking  into
  399. consideration all the dependencies and the specified start  on/after
  400. date.
  401.  
  402. For  a  set  of dependent tasks there will be a number of the  tasks
  403. that  are  critical to the end of the project. If any one  of  these
  404. tasks  is  late  then the end of the project will be delayed.  These
  405. tasks  are  described as being on the critical path. It is important
  406. to  know the critical path for two reasons. Firstly, it is useful in
  407. identifying the tasks that may be worth adding extra resource to, in
  408. order  to  bring the project in sooner. Secondly, it  is  useful  in
  409. highlighting  those  tasks that will need to be monitored  carefully
  410. when  the  project  is in progress in order for the  project  to  be
  411. completed  on  time.  Plan has an option which  will  calculate  the
  412. critical path.
  413.  
  414. 3. FAST START TUTORIAL
  415.  
  416. This  section describes, by way of an example, how to use  the  main
  417. features  within  Plan. It includes an example of creating  a  plan,
  418. adding resources and tasks, and updating tasks.
  419.  
  420. Plan  has  many features and it is not possible to describe  all  of
  421. these  features  within a short section such as this.  This  section
  422. includes enough to get started, as you become more familiar you  may
  423. want to explore the rest of the manual to find out what else you can
  424. do with Plan.
  425.  
  426. 3.1 Creating a new plan
  427.  
  428. If  Plan has not been installed or is not visible as an icon on  the
  429. Psion  system  screen then refer to the installation section  before
  430. proceeding.
  431.  
  432. When  first  starting  Plan it will create a default  resource  file
  433. which has a single resource called "General". The work days for this
  434. resource  will  be set to the work days set within  the  Psion  Time
  435. application. The following tutorial assumes that the work  days  are
  436. Monday  to  Friday  with Saturday and Sunday  as  non-working  days.
  437. Before  proceeding ensure that the work days are set accordingly  by
  438. going  to  the  Time application and selecting the  "Workdays"  menu
  439. option from the "Settings" menu.
  440.  
  441. On  the Psion, go to the system screen and position the cursor below
  442. the Plan icon. From the "File" menu on the system screen select "New
  443. file".  In the dialog which appears enter a file name such as "Test"
  444. and press Enter.
  445.  
  446. Plan will start up and display a screen with a top line reading TASK
  447. DESCRIPTION  WORK,... Under the top line there will be a highlighted
  448. line  or  cursor. This is one of the many different views  available
  449. within Plan.
  450.  
  451. 3.2 Creating a new resource
  452.  
  453. Start by creating a new resource. To do this, select the "Make" menu
  454. option from the "Resource" menu. Enter the name for the resource  as
  455. "Res1".  A second dialog will appear. In this dialog set the maximum
  456. units  value  to 1 which indicates that this resource  represents  a
  457. single  person.  A  resource may be used to  represent  a  group  by
  458. setting  the maximum units to a value greater than 1. Set  the  cost
  459. per hour to 5. Plan will calculate the cost of the project using the
  460. resource charge rates as entered here.
  461.  
  462. Two  more dialogs will appear prompting for the work hours  for  the
  463. resource. The first dialog shows the start times for each day of the
  464. week  and the second dialog shows the end times. Leave these at  the
  465. default of 9am to 5pm throughout the whole week. Press enter and the
  466. resource will be created.
  467.  
  468. From  the  diamond menu select the "Holiday view" option. This  will
  469. display  the  holidays  for the newly created resource.  These  will
  470. default  to the same holidays as the General resource which in  turn
  471. will  initially have been set using the rest days set in  the  Psion
  472. Time  application. The cursor keys may be used to move from one  day
  473. to  the  next  and the enter key will toggle a holiday on  and  off.
  474. Leave all the holidays unchanged for the time being.
  475.  
  476. 3.3 Creating tasks
  477.  
  478. Now  enter a new task. From the diamond menu select the "Task  List"
  479. menu option.
  480.  
  481. In the task list view each task is shown on one line of the display.
  482. Each  task  has  a number of associated fields. The left  and  right
  483. cursor keys will shift the right hand side of the task list view  to
  484. display the various fields for each task.
  485.  
  486. First  ensure that Caps lock is turned off and then press the  enter
  487. key. A dialog will appear prompting for the task details. Enter  the
  488. values as shown:
  489.                                   
  490.        Id                T1
  491.        Description       Task 1
  492.        Start on/after    1 Apr 1996, 09:00am
  493.        Work              3 days
  494.        
  495. When the enter key is used a second dialog will appear prompting for
  496. the  details of the resources to be assigned to the task. Update the
  497. dialog as follows and press enter:
  498.                                   
  499.        Resource          Res1
  500.        Rate (%)          100
  501.  
  502. The  new task will be created and the screen will update to show the
  503. entered  and calculated values. Note that the end date for the  task
  504. has  been calculated by Plan using the start on/after date  and  the
  505. work.  The end should be displayed as 5pm on 3 Apr 1996. The  labour
  506. cost is also calculated and displayed as 120.
  507.  
  508. From  the  diamond menu select the Gantt chart. Press the space  bar
  509. which will refresh the display on the right hand side to display the
  510. current  task.  This  shows the task on one line  with  a  graphical
  511. representation  of the task on the right hand side  of  the  screen.
  512. Press  the  down arrow to move the highlighted line, or  cursor,  to
  513. below task T1. Note how the graphical bar extends from the start  of
  514. the task to the end, with the holidays shaded.
  515.  
  516. Now enter a second task by pressing enter with the cursor below task
  517. T1. Create a new task with the following values:
  518.  
  519.        Id                T2
  520.        Description       Task 2
  521.        Start on/after    1 Apr 1996, 09:00am
  522.        Work              1 day
  523.        Resource          Res1
  524.        Rate (%)          100
  525.        
  526. The  new  task  will be shown below task T1 and  will  be  shown  as
  527. starting on the 1 Apr 1996 and ending at the end of the same day.
  528.  
  529. 3.4 Setting dependencies
  530.  
  531. Now set the start of task T2 to depend upon the end of task T1. With
  532. task  T2  current, i.e. highlighted, select the "Dependencies"  menu
  533. option from the "Task" menu. Set the first task Id to T1 by pressing
  534. the  tab key and selecting T1. When the second dialog appears  leave
  535. the  "Lag-T1" field set to "None" meaning that task T2  will  follow
  536. straight after task T1. When the enter key is pressed task  T2  will
  537. be recalculated to start after task T1.
  538.  
  539. 3.5 Summary tasks
  540.  
  541. Now enter a summary task for task T1 and T2. Ensure that task T1  is
  542. current  and press shift-enter to insert a new task. The  enter  key
  543. edits the current task, or creates a new task if no task is current,
  544. and  shift-enter  inserts a new task immediately above  the  current
  545. task.  Set the Id to S1 and the description to "Summary task". Leave
  546. all  the other fields unchanged. A new task will be inserted at  the
  547. top of the list.
  548.  
  549. At  the moment all the tasks are normal tasks and we need to make T1
  550. and  T2  sub-tasks of the new task. To do this, make T1 current  and
  551. press  control-right arrow. This will indent T1 and place  a  bullet
  552. next  to  the  description. T1 is now a sub-task  and  S1  has  been
  553. changed from a normal task into a summary task. Repeat this so  that
  554. T2 is also a sub-task.
  555.  
  556. 3.6 Updating a task
  557.  
  558. To  demonstrate how Plan automatically recalculates tasks, edit task
  559. T1 so that the start on/after date is 2 Apr 1996 at 09:00am. This is
  560. done by making task T1 current and pressing enter. When edited, task
  561. T1, T2 and the summary task will be recalculated automatically.
  562.  
  563. 3.7 Tracking work done
  564.  
  565. Imagine  that task T1 is underway and that it is now the morning  of
  566. the  4  Apr  1996. From the "Task" menu select "Set work  done"  and
  567. choose the option "Set by time...". This dialog allows the work done
  568. on  a  task so far to be set. Enter the work done as 2 days and  set
  569. the  "Done up to start of" value to 4 Apr 1996. The bar on the Gantt
  570. chart representing the task will be shaded to indicate the % of  the
  571. work done so far.
  572.  
  573. 3.8 Reviewing a task when it is underway
  574.  
  575. Suppose that whilst task T1 is underway you receive information from
  576. resource  "Res1" that there are still 2 more days work  left  to  do
  577. rather  than  the  1  day  which  is  currently  planned.  Plan  can
  578. recalculate the end using the work done so far and information about
  579. the   remaining   work.   From  the  "Task"  menu   select   "Review
  580. calculation".  Set  the  remaining work to  2  days  and  leave  the
  581. remaining  work  rate set to 100%. The task will be recalculated  to
  582. end  on  the  5 Apr 1996. To display all the tasks press psion-Z  to
  583. zoom  the view out. In the Gantt chart the psion-Z and psion-z  keys
  584. zoom  in  and out and the left and right arrow keys move the display
  585. left and right. The space bar may be used to recenter the display to
  586. show the current task.
  587.  
  588. 3.9 Task end/work/rate calculation
  589.  
  590. Imagine now that task T1 has been completed and actually finished at
  591. 5pm  on  Monday  8 Apr 1996. So you know when the task  started  and
  592. ended, plus the fact that Res1 worked on the task 100%. Normally  it
  593. is  the end date for a task that needs to be calculated, but in this
  594. case  it  is more appropriate to calculate the work from the  start,
  595. end  and  rate. To get Plan to do this for you, ensure T1 is current
  596. and select the "End/work/rate" menu option from the "Task" menu. Set
  597. the  calculate value to "Work". Now edit the task by pressing enter.
  598. Note  how previously the start date and work fields were shown.  Now
  599. it  is  the start and end dates that need to be entered. Update  the
  600. end  to 5pm on 8 Apr 1996. The task will be adjusted accordingly and
  601. the work recalculated as 5 days.
  602.  
  603. To mark the task T1 as complete set the work done to 100% using "Set
  604. by %..." from the "Set work done_" menu option on the "Task" menu.
  605.  
  606. 3.10 Views
  607.  
  608. To save the plan select "Save" from the "File" menu.
  609.  
  610. Now  look  at  the  other views available in Plan using  either  the
  611. diamond key or the diamond menu. In all the task based views the  up
  612. and down arrow keys change the current task.
  613.  
  614. The task list view shows one task on each line of the display. Press
  615. the left and right arrow keys to shift the fields shown on the right
  616. hand side of the screen left and right.
  617.  
  618. The Gantt screen has already been seen during the tutorial.
  619.  
  620. The  PERT  screen  will initially appear blank. To layout  the  PERT
  621. chart  select the PERT view and choose the "Layout pert" menu option
  622. from the "View" menu. Leave the "X mag" and "Y shift" values set  to
  623. 1.  In  the PERT chart each task is shown as a box with dependencies
  624. indicated  by  lines between tasks. The left and  right  arrow  keys
  625. shift  the  PERT chart left and right and the Pg Up and Pg  Dn  keys
  626. shift the display up and down. The zoom menu options may be used  to
  627. alter the scale.
  628.  
  629. The  resource usage view shows the working hours for a  resource  as
  630. well as the allocation of the resource to tasks.
  631.  
  632. 3.11 Example Plan
  633.  
  634. An  example plan and resource file are supplied which may be used to
  635. further experiment with Plan.
  636.  
  637. 4. KEY FEATURES
  638.  
  639. Plan has the following key features:
  640.  
  641.  - A separate file for each project plan with either plan specific
  642.    or a shared resource file.
  643.  - Up  to  200  tasks may be entered, each having the  following
  644.    details:
  645.    - Id
  646.    - description
  647.  - work
  648.  - up to four assigned resources per task
  649.  - rate of work for each assigned resource
  650.  - start on/after date and time
  651.  - start date and time
  652.  - end date and time
  653.  - calculation method (end, work or rate)
  654.  - work done
  655.  - labour and fixed costs
  656.  - saved work, start and end dates and times for future reference
  657.  - user floating point value and text fields
  658.  - Calculation of end date and time, work, or work rates for each
  659.    task.
  660.  - A start constraint may be specified, i.e. the task must start
  661.    on/after the given date.
  662.  - A  task  may be dependent upon up to eight other tasks,  with
  663.    specified lag times with each dependency. Plan will automatically
  664.    calculate  the start of each task from the dependency  and  start
  665.    on/after date.
  666.  - Task  tracking.  The  actual  work  done  may  be  input  and
  667.    incrementally changed as work progresses.
  668.  - A task may be re-estimated taking into account the work already
  669.    done and the work remaining.
  670.  - Calculation of critical path.
  671.  - Accuracy  down  to the second with an option  which  controls
  672.    whether dates or dates and times are entered and displayed.
  673.  - Tasks  may  be grouped under a summary task whose fields  are
  674.    calculated automatically from the sub-tasks. Tasks may be nested up
  675.    to eight levels deep.
  676.  - The labour costs are calculated automatically for a task along
  677.    with the total cost for the project.
  678.  - A memo may be attached to each task. Memos are edited using the
  679.    Psion Word application which is started via Plan.
  680.  - Any number of resources may be input, (subject to memory limits
  681.    imposed  by  the Psion operating system). Each resource  has  the
  682.    following properties:
  683.    - name
  684.    - maximum units available
  685.    - labour charge per hour
  686.    - a three year holiday calendar
  687.    - times for the start and end of work for each week day
  688.  - Plan can check and highlight any over-allocated resources.
  689.  - Plan will count resource holidays in a given period.
  690.  - A Gantt chart view.
  691.  - A PERT chart view.
  692.  - A resource allocation histogram view.
  693.  - Auto layout of tasks in the PERT chart.
  694.  - Sorting of tasks by a number of attributes.
  695.  - Export data to the Psion Agenda application.
  696.  - Print Gantt and PERT charts on a postscript printer.
  697.  - Transfer projects between Plan and Microsoft Project.
  698.