Encoding:
Text File  |  1987-01-28  |  9.7 KB  |  316 lines

  1. <CMD><*1203
  2. ┌────────────────────────────────────────────────┐
  3. │             Lesson 7:  Gantt chart             │
  4. └────────────────────────────────────────────────┘
  5.  
  6.      In this lesson you'll:
  7.  
  8.      ■  look at the Gantt chart for HiTech
  9.  
  10.      ■  add the names of those responsible
  11.         for each task
  12.  
  13.      ■  select and sort the tasks displayed
  14.         in the chart
  15.  
  16. ──────────────────────────────────────────────────
  17.                   Press Spacebar><CMD>
  18. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1203
  19.  
  20.      You've used the work breakdown structure,
  21.      the task list, and the PERT chart to put
  22.      information into the HiTech project.
  23.      Now it's time to look at its ~Gantt chart~2
  24.      for a different view of the project.
  25.  
  26.      A Gantt chart shows tasks and milestones
  27.      laid out along a timescale.  You'll see 
  28.      planned starts and finishes, durations,
  29.      constraints, and slack.
  30.  
  31. ──────────────────────────────────────────────────
  32.                   Press Spacebar><CMD>
  33. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1205
  34.  
  35.      So that you can take a look at a Gantt
  36.      chart, I'll get the HiTech project for
  37.      you.
  38.  
  39.      Just sit back for a moment and wait for
  40.      the next Tutorial window.
  41.  
  42. ──────────────────────────────────────────────────
  43.                   Press Spacebar><CMD>
  44. <XFLD><Ctrl5><XFLD><ENDDEF>
  45. 5<F2><ENTER>HITECH1<F10><CHOME><CMD><*1412
  46. This is the PERT chart for HiTech.  It includes
  47. the milestones and durations that we entered in an
  48. earlier lesson.  Let's take a look at its Gantt
  49. chart.
  50.  
  51. First, pull down the Graphs menu.
  52. ──────────────────────────────────────────────────
  53.                      Press F2><CMD>
  54. <XFLD><F2><XFLD><ENDDEF><CMD><*1412
  55. Select ~Gantt chart~2 from the Graphs menu.
  56. ──────────────────────────────────────────────────
  57.                       Type ~2~1><CMD>
  58. <XFLD>2<XFLD><CMD><*4405
  59. This is the Gantt chart for
  60. HiTech.  A Gantt chart lists
  61. all the tasks and milestones
  62. for a project on the left of
  63. the chart.  (Some tasks are
  64. out of view right now.)
  65. ────────────────────────────
  66.        Press Spacebar><CMD>
  67. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4205
  68. Normally, HTPM lists all
  69. tasks and milestones, but
  70. you can ask it to list just
  71. tasks, just milestones, or
  72. just overallocated tasks.
  73. ────────────────────────────
  74.        Press Spacebar><CMD>
  75. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4205
  76. Tasks and milestones are
  77. listed in the order of their
  78. planned start dates.  You
  79. can change the order of the
  80. tasks so that they are listed
  81. by any one of many factors.
  82. ────────────────────────────
  83.        Press Spacebar><CMD>
  84. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4205
  85. At the top of the Gantt is
  86. a timescale.  HTPM automati-
  87. cally divides the timescale
  88. in one-week units.  You can
  89. change the timescale, too,
  90. if you like.
  91. ────────────────────────────
  92.        Press Spacebar><CMD>
  93. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4205
  94. To interpret a Gantt chart,
  95. you should understand a few
  96. of the simple symbols HTPM
  97. uses on the chart.
  98. ────────────────────────────
  99.        Press Spacebar><CMD>
  100. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4205
  101. HTPM uses triangles to show
  102. milestones on a Gantt.  If a
  103. milestone has no slack, the
  104. triangles are close together,
  105. forming a diamond.
  106. ────────────────────────────
  107.        Press Spacebar><CMD>
  108. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4205
  109. Tasks are represented by
  110. horizontal lines and bars.
  111. ────────────────────────────
  112.        Press Spacebar><CMD>
  113. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4205
  114. If the line extends to the
  115. right of the bar, the task
  116. has some slack.  The task
  117. ~Staff~2 has some slack.
  118. ────────────────────────────
  119.        Press Spacebar><CMD>
  120. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4205
  121. But the task ~PlnBooth~2 has
  122. no slack.  The line and the
  123. bar are the same length.
  124. ────────────────────────────
  125.        Press Spacebar><CMD>
  126. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4205
  127. Under each task and mile-
  128. stone name, HTPM displays
  129. a ~tag~2 showing the duration
  130. of the task or the date of
  131. the milestone.  We're going
  132. to add another tag to the
  133. Gantt chart.
  134. ────────────────────────────
  135.        Press Spacebar><CMD>
  136. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4215
  137. Let's add the names of those
  138. responsible for each task to
  139. the Gantt chart.
  140. ────────────────────────────
  141.        Press Spacebar><CMD>
  142. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4216
  143. Pull down the Format menu.
  144. ────────────────────────────
  145.           Press F5><CMD>
  146. <XFLD><F5><XFLD><ENDDEF><CMD><*3717
  147. Select ~Tag PERT chart/Gantt chart~2.
  148. ─────────────────────────────────────
  149.                Type ~7~1><CMD>
  150. <XFLD>7<XFLD><ENDDEF><CMD><*6112
  151. Leave the
  152. default of
  153. ~Tasks~2.
  154. ──────────
  155. Press F10><CMD>
  156. <XFLD><F10><XFLD><CMD><*0618
  157. In this fill-in, you can choose as many as five different tags to
  158. be listed under each task.
  159. ─────────────────────────────────────────────────────────────────
  160.                        Press Spacebar><CMD>
  161. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*0618
  162. Right now, HTPM displays just the planned duration under each
  163. task.
  164. ─────────────────────────────────────────────────────────────────
  165.                        Press Spacebar><CMD>
  166. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*0618
  167. To include the person responsible, move the cursor to the next
  168. column.
  169. ─────────────────────────────────────────────────────────────────
  170.                           Press Tab><CMD>
  171. <XFLD><TAB><XFLD><ENDDEF><CMD><*5009
  172. Move the cursor
  173. down so that it
  174. is on the item
  175. ~Responsible~2.
  176. ─────────────────
  177. Press down arrow
  178.   eight times><CMD>
  179. <XFLD><DN><DN><DN><DN><DN><DN><DN><DN><XFLD><ENDDEF><CMD><*5009
  180. Now indicate that
  181. it should be the
  182. second tag.
  183. ─────────────────
  184.  Type ~2~1 and
  185.    press F10><CMD>
  186. <XFLD>2<F10><XFLD><CMD><*4205
  187. Now the Gantt chart shows
  188. that the Sales Assistant is
  189. responsible for the task
  190. ~Staff~2.
  191. ────────────────────────────
  192.        Press Spacebar><CMD>
  193. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4205
  194. Let's make one final change
  195. to the Gantt so that it shows
  196. just the tasks.  While we're
  197. at it, let's list the tasks
  198. alphabetically by the person
  199. responsible for each.
  200. ────────────────────────────
  201.        Press Spacebar><CMD>
  202. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4216
  203. Pull down the Format menu.
  204. ────────────────────────────
  205.           Press F5><CMD>
  206. <XFLD><F5><XFLD><ENDDEF><CMD><*4216
  207. Select ~Sort/Select Gantt~2
  208. ~chart~2.
  209. ────────────────────────────
  210.            Type ~5~1><CMD>
  211. <XFLD>5<XFLD><HOME><ENDDEF><CMD><*3414
  212. On this fill-in, select
  213. ~Tasks only~2.
  214. ────────────────────────────
  215.   Press down arrow and then
  216.              F10><CMD>
  217. <XFLD><DN><F10><XFLD><CMD><*3207
  218. At the Sort/Select fill-in,
  219. you indicate the order in
  220. which tasks should be listed.
  221.  
  222. By specifying a range, you
  223. can also limit the tasks
  224. to those that meet your
  225. criteria, such as tasks that
  226. start within a specific time
  227. period.
  228. ────────────────────────────
  229.        Press Spacebar><CMD>
  230. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*3207
  231. Right now, HTPM displays
  232. tasks according to their
  233. planned start date.  The
  234. tasks are listed in ascend-
  235. ing order; that is, from
  236. earliest to latest date.
  237. (Note the ~1A~2 in the ~Sort~2
  238. ~order~2 column.)  Let's erase
  239. this sort order.
  240. ────────────────────────────
  241.       Press down arrow><CMD>
  242. <XFLD><DN><XFLD><ENDDEF><CMD><*3207
  243. Now erase the ~1A~2.
  244. ────────────────────────────
  245.         Press Ctrl-E><CMD>
  246. <XFLD><CtrlE><XFLD><ENDDEF><CMD><*3207
  247. We're ready to specify a
  248. different sort order for the
  249. chart.  But, we can't see
  250. all the items that you can
  251. use for sorting and selecting
  252. tasks.  In fact, the item we
  253. want, ~Responsible~2 is off
  254. the screen right now.  Let's
  255. move the cursor down to the
  256. next screen.
  257. ────────────────────────────
  258.      Press the PgDn key><CMD>
  259. <XFLD><PGDN><XFLD><CMD><*3207
  260. Move the cursor to the ~Sort~2
  261. ~order~2 column opposite the
  262. item ~Responsible~2.
  263. ─────────────────────────────────
  264. Press left arrow, then down arrow><CMD>
  265. <XFLD><LFT><DN><XFLD><ENDDEF><CMD><*3010
  266. Type the sort order.
  267. ────────────────────────────
  268.           Type ~1A~1><CMD>
  269. <XFLD>1A<XFLD><ENDDEF><CMD><*3010
  270. And confirm that the fill-
  271. in is complete.
  272. ────────────────────────────
  273.          Press F10><CMD>
  274. <XFLD><F10><XFLD><CMD><*1416
  275. HTPM takes a moment to reformat the Gantt chart.
  276. Then it displays it with just the information we
  277. requested.
  278. ──────────────────────────────────────────────────
  279.                   Press Spacebar><CMD>
  280. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1416
  281. Only the tasks are listed.  And tags, displayed
  282. under the task names, show the person responsible
  283. for the task.
  284. ──────────────────────────────────────────────────
  285.                   Press Spacebar><CMD>
  286. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1416
  287. The tasks aren't listed by start date any more.
  288. Instead, they're listed alphabetically by the
  289. person responsible.
  290. ──────────────────────────────────────────────────
  291.                   Press Spacebar><CMD>
  292. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1416
  293. Now return to the main menu.
  294. ──────────────────────────────────────────────────
  295.                   Press Esc twice><CMD>
  296. <XFLD><ESC><ESC><XFLD><CMD><*1219
  297. Let's briefly review this lesson.
  298. ──────────────────────────────────────────────────
  299.                   Press Spacebar><CMD>
  300. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1205
  301.                   ~In summary ...~1
  302.  
  303.      ■  Display the Gantt chart to see your
  304.         tasks and milestones laid out across
  305.         a timescale.
  306.  
  307.      ■  Use the Format menu to change the
  308.         timescale display, sort and select
  309.         the tasks and milestones in the
  310.         chart, and add tags beneath each
  311.         task and milestone name.
  312.  