- Newsgroups: sci.space.news
- Path: sparky!uunet!elroy.jpl.nasa.gov!ames!dont-send-mail-to-path-lines
- From: yee@atlas.arc.nasa.gov (Peter Yee)
- Subject: Shuttle Status for 01/20/93 (Forwarded)
- Message-ID: <1993Jan21.214833.25109@news.arc.nasa.gov>
- Apparently-To: sci-space-news@ames.arc.nasa.gov
- Followup-To: sci.space
- Originator: yee@atlas.arc.nasa.gov
- Sender: usenet@news.arc.nasa.gov
- Reply-To: yee@atlas.arc.nasa.gov (Peter Yee)
- Organization: NASA Ames Research Center, Moffett Field, CA
- Date: Thu, 21 Jan 1993 21:48:33 GMT
- Approved: sci-space-news@ames.arc.nasa.gov
- Lines: 52
-
- SPACE SHUTTLE STATUS REPORT
- Wednesday, January 20, 1993
-
-
- George H. Diller
- Kennedy Space Center
- 407/867-2468
-
-
- Vehicle: OV-102/Columbia
- Current location: OPF Bay 2
- Mission: STS-55/Spacelab D-2 Inclination: 28.45 degrees
- Launch timeframe: February, wk 4 Nominal Landindg Site: KSC
- Mission Duration: 8 days 22 hours Crew Size: 7
-
-
- IN WORK TODAY:
-
- - installation of Spacelab tunnel
- - hydraulic test of flight controls
- - position flight control elements for rollover
- - orbiter/external tank door functional test
- - orbiter aft compartment closeouts
- - orbiter mid-body closeouts
-
- WORK COMPLETED:
-
- - Spacelab D-2 Interface Verification Test (IVT)
- - payload bay cleaning
- - ammonia boiler servicing
-
-
- WORK SCHEDULED:
-
- - payload bay door radiator inspections Saturday
- - Crew Equipment Interface Test on Sunday
-
-
- SPECIAL TOPICS--Endeavour post landing analysis:
-
- OV-105 touched down at 08:38:17 a.m. EST on Tuesday, landing
- approximately 1,500 feet from the Runway 33 threshhold about
- three feet right of centerline, and rolling out approximately
- 8,700 feet.
-
- Brake and tire wear was normal, except for a cut 5/16th-inch
- deep and two plys of scuffing on the right inboard tire. There
- were 57 debris impacts, with 13 greater than one inch. Four to
- five tiles are expected to be replaced.
-
- Endeavour arrived at OPF Bay 1 at approximately 2 p.m. Tues-
- day where deservicing is now in work.
-