home
***
CD-ROM
|
disk
|
FTP
|
other
***
search
/
Your Business Pak
/
BusinessPak2.iso
/
Pca
/
_SETUP.1
/
2671.BLD
< prev
next >
Wrap
Text File
|
1997-07-22
|
5KB
|
208 lines
#2671
@001 Enter the name of the OWNER:
~Enter the full name of all the owners of the property.
~If the contracting job is being done on behalf of a tenant
~enter the name of the tenant instead.
@002 Enter the name of the CONTRACTOR:
~Enter the full name of the contractor.
@100 Enter the description of the work to be performed:
~Enter a full and complete description of the work to be
~performed. This should include if at all possible drawings.
@101 Enter estimated completion schedule:
~Enter the schedule for the work to be performed.
!102 Enter the contract price:
~Specify the full price for the job in numerals. Do not
~use the "$" sign or commas. For example: 5000.00 is a valid
~entry.
#2672 Do you want to specify materials to be used?
~Enter the description of the type of materials to be used.
~This should include brand names. General descriptions like
~"first class" are not useful.
#if#2672
@300 Enter type of materials to be specified:
~Enter the materials for which a detailed specification will
~be provided by type. For example: roofing shingles. The next
~choice will allow the exact specifications to be entered.
@301 Enter specifications:
~Enter the brand name and models to be used.
#endif
#2673 Will the contractor pay for permits?
~Select yes if the contractor has included the costs of the
~permits in the contract price, no otherwise.
#2674 Will contractor be required to provide proof of insurance?
~All reputable contractors have insurance and are willing to
~provide proof of insurance.
#if#2674
!103 Enter insurance limits required (in numerals):
~Enter in numerals, without the "$" sign or commas the amount
~of insurance that the contractor must carry.
#endif
#2675/#2676/#2677 Draws will be based on:
~We provide three choices for the payment schedule.
1/3 Rough in;1/3 inspection;1/6;1/6
Weekly draw on per centage of completion
Joint checks on materials; 1/3;1/3- 1/6,1/6 on labor
#2678 Is contractor required to remove trash?
~Contracts vary as to whether the contractor removes the
~construction debris or the owner does so. Select the proper
~choice.
#2679
#end control section
#2671
/* Para. 2671: Contract for remodeling, large */
CONTRACTING AGREEMENT
@001, referred to as OWNER, and @002, referred to as CONTRACTOR,
agree as follows:
CONTRACTOR shall perform the following services for OWNER:
@100
on the following estimated schedule:
@101
for the following price: $ @102 (!102 dollars)
Contractor shall be responsible for the following in addition to
the workman like performance of the work stated above:
#2672
/* Para 2672: Spec of materials */
The materials used for the following areas:
@300
shall meet the following respective specifications, or be
equivalent to the following manufacturer's product lines
described:
@301
#2673
/* Para 2673: Permits */
Provision of all permits required for the services to be performed
above.
#2674
/* Para 2674: Insurance*/
Provision of worker's compensation insurance, general liability
insurance in a minimum amount of $ @103 (!103 dollars).
#2675
/* Para. 2675: Draw sked */
The stipulated contract price shall be paid as follows:
1/3 on rough in; 1/3 on first inspection and 1/6 on final
inspection and 1/6 on final inspection and completion of all
appearance/punch list in items.
#2676
/* Para. 2676: Weekly draw based on per centage of completion*/
The stipulated contract price shall be paid as follows:
A weekly draw based upon per centage of completion, less a
retainage of 10% per cent, which shall be paid on final
inspection and completion of appearance/punch list items.
#2677
/* Para. 2677: Bills for materials */
The stipulated contract price shall be paid as follows:
When bona fide bills for materials are presented the same shall
be paid directly by the OWNER within the terms provided. Labor
shall be paid as follows:
1/3 on rough in; 1/3 on inspection; 1/6 on completion; 1/6 on
final inspection and completion of appearance/punch list items.
#2678
/* Para. 2678: Removal of trash */
The CONTRACTOR shall daily remove all trash and debris from the
premises.
#2679
/* Para. 2679--- closer */
This is the entire agreement between the parties and this
agreement may only be altered in writing.
Dated: _________________________
____________________________________________________
@001
____________________________________________________
@002