- From: pmk@prometheus.UUCP (Paul M. Koloc)
- Newsgroups: sci.physics.fusion
- Subject: Re: Plasmak/Paul Koloc
- Message-ID: <1992Aug19.113435.27357@prometheus.UUCP>
- Date: 19 Aug 92 11:34:35 GMT
- References: <12AUG199216475632@lims02.lerc.nasa.gov>
- Reply-To: pmk@prometheus.UUCP (Paul M. Koloc)
- Organization: Prometheus II, Ltd.
- Lines: 24
-
- In article <12AUG199216475632@lims02.lerc.nasa.gov> edwlt12@lims02.lerc.nasa.gov (MIKE JAMISON) writes:
- >I hate to interrupt all these cool flames, but, what the heck :)
- >
- >The last time someone asked Paul what he was up to, he responded that, if
- >all went well, they'd be testing their device sometime in August (I'm going
- >from memory here, I think it was August...)
- >
- >Well, it's sometime in August, Paul, what's going on???
- >
- >Mike Jamison
-
- We are have slipped 6 to eight weeks for a number of reasons.
- Still the commencing of diagnostic work will require three months
- before we have enough data and information (analysis) to start pulling
- chains.
-
- I would say to query again in around the end of January or into February.
-
- +---------------------------------------------------------+**********+
- | Paul M. Koloc, President, Prometheus II, Ltd. +Commercial*
- | Bx 222, College Park, MD 20740-0222 ***FUSION***
- | mimsy!promethe!pmk pmk%prometheus@mimsy.umd.edu ***in the***
- | (301) 445-1075 promethe=prometheus **Nineties**
- +---------------------------------------------------------************
-