Task Number Task Name Start Stop Len !----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!
1.11.001 TASK 1 02/14/89 04/02/89 47 *********************** 04/02 WORK
==> Actual Time Spent 02/12/89 03/23/89 39 =================== 03/23
# 1- PERSON - - - | +
PERSON --> 300 M/h
Other Direct Costs --> $ 1350.00
Man-hour Costs --> $ 15000.00
Task Costs --> $ 16350.00
1.11.002 NEW TASK 03/22/89 04/26/89 35 ***************** 04/26
# 4- STAFF 1 - - - | +
STAFF 1 --> 26 M/h
Other Direct Costs --> $ 3373.00
Man-hour Costs --> $ 1202.76
Task Costs --> $ 4575.76
1.11.005 NEW TASK 08/12/89 09/14/89 33 **************** 09/14