The Project Task List is displayed to the left hand side of the Project mode. It is very similar in behaviour to the Task List in Diary mode.

OfficeTalk lets you record one or more of the following attributes against each project task:

A description of the task

A priority

A deadline

A planned start date

A planned duration

The percentage completion

Detailed notes about the task

Additionally, you may add any number of user defined fields to the project task data type which means that you can store almost any data that you like with each task. For more information on adding user defined fields to projects and project tasks see Administering Custom Data.

More:

Creating a New Project Task

Planning a Project Task

Specifying a Deadline

Prioritising Your Tasks

Structuring Your Task List

Categorising Project Tasks

Project Task List Columns

Importing and Exporting Project Data

Importing an MPX File