  1.  
  2.  
  3.  
  4.                       ╔══════════════════════════════╗
  5.                       ║ E A S Y  P R O J E C T  (tm) ║
  6.                       ║                              ║
  7.                       ║         USER GUIDE           ║
  8.                       ║         Version 2.5          ║
  9.                       ╚══════════════════════════════╝
  10.  
  11.                  A Project Management and Tracking System
  12.               for the I.B.M. Personal Computer and Compatibles
  13.  
  14.  
  15.  
  16.                   (c) Copyright 1987, 1988 Parcell Software
  17.                             All Rights Reserved
  18.  
  19.  
  20.  
  21.  
  22.  
  23.  
  24.  
  25.  
  26.  
  27.  
  28.  
  29.  
  30.  
  31.  
  32.  
  33.  
  34.  
  35.  
  36.  
  37.                               Parcell Software
  38.                             948 Manchester Course
  39.                               Geneva, Il  60134
  40.                                (312) 232-6328
  41.  
  42.                            CompuServe ID:  72250,1356
  43.  
  44.  
  45.  
  46.  
  47.  
  48.  
  49.                                               ┌─────────┐
  50.                                         ┌─────┴───┐     │              (tm)
  51.                                       ──│         │o    │──────────────────
  52.                                         │   ┌─────┴╨──┐ │  Association of
  53.                                         │   │         │─┘  Shareware
  54.                                         └───│    o    │    Professionals
  55.                                       ──────│    ║    │────────────────────
  56.                                             └────╨────┘    MEMBER
  57.  
  58.  
  59.  
  60.  
  61.                           E A S Y  P R O J E C T  (tm)
  62.  
  63.  
  64.                                Registration
  65.  
  66.  
  67.     Easy Project is a Shareware program.
  68.  
  69.     You are encouraged to copy and share this program with other users. 
  70.     No fee can be charged for such copying and distribution except for
  71.     a nominal charge to defray expenses.
  72.  
  73.     If you find this program useful, we trust you to send a $39.00
  74.     payment. Registration covers a single PC only.  Site licenses
  75.     available upon request.
  76.  
  77.     Shareware constitutes a viable, low cost alternative to many
  78.     commercially available products.  Shareware distribution gives users
  79.     an opportunity to try software before buying it.  If you try a
  80.     Shareware program and continue to use it, you are expected to
  81.     register.  Your support is important and greatly appreciated.
  82.  
  83.     All registered users will receive:
  84.                 - Latest version of Easy Project with Shareware screen
  85.                   disabled
  86.                 - Printed User Guide
  87.                 - Notification of updates
  88.                 - Free technical support
  89.  
  90.     Please use the form below when registering your copy.
  91.  
  92.    -----------------------------------------------------------------------
  93.  
  94.                           E A S Y  P R O J E C T
  95.                                    2.5
  96.                              Registration Form
  97.  
  98.  
  99.     Name:                                              Date:          
  100.  
  101.     Address:                                     
  102.  
  103.                                                 
  104.  
  105.                                                     
  106.     Where did you hear about Easy Project:
  107.  
  108.  
  109.     Registration is $39.00 and covers a single PC only.
  110.     Please send a check or money order to :
  111.  
  112.                              Parcell Software
  113.                            948 Manchester Course
  114.                              Geneva, Il  60134
  115.  
  116.  
  117.  
  118.  
  119.  
  120.                        E A S Y  P R O J E C T  (tm)
  121.  
  122.  
  123.                                Introduction
  124.  
  125.  
  126.          Easy Project is a project management tool for the I.B.M. and
  127.          compatible personal computers.  Easy Project is designed to be an
  128.          easy to learn, practical, and efficient method for planning,
  129.          tracking, and controlling all types of projects.
  130.  
  131.          Easy Project features:
  132.  
  133.              1.  User defined project phases (20 maximum)
  134.              2.  Unlimited number of resources per project
  135.              3.  User defined tasks (1000 per project)
  136.              4.  User defined subordinate tasks or items (100 per task)
  137.              5.  Fast data entry with multiple resource assignments
  138.                  per task
  139.              6.  Automatic scheduling and schedule maintenance
  140.              7.  Gantt charts showing planned vs. actual dates
  141.                  with variable scales
  142.              8.  Extensive reporting including work plans, status reports,
  143.                  and earned value accrual reporting
  144.              9.  Online context sensitive help screens
  145.             10.  dBASE III file compatibility
  146.  
  147.          Sample data is provided to assist in learning Easy Project.
  148.  
  149.  
  150.          Disclaimer
  151.  
  152.              Parcell Software specifically disclaims any warranty, either
  153.              expressed or implied, including but not limited to the
  154.              implied warranties of merchantability and fitness for a
  155.              particular use.
  156.  
  157.              In no event shall Parcell Software be liable for any special,
  158.              consequential, or other damages, including loss of profit
  159.              arising out of the us of this program.
  160.  
  161.  
  162.          Trademarks
  163.  
  164.              Easy Project is a trademark of Parcell Software
  165.              I.B.M. is a registered trademark of the I.B.M Corporation.
  166.              dBASE III is a registered trademark of Ashton-Tate, Inc.
  167.  
  168.  
  169.  
  170.  
  171.                        E A S Y  P R O J E C T  (tm)
  172.  
  173.  
  174.                             System Requirements
  175.                             
  176.  
  177.      Hardware
  178.           I.B.M. PC/XT/AT/PS2 or 100% Compatible with at least 256K RAM
  179.  
  180.      Monitor
  181.           Any
  182.  
  183.      Printer
  184.           Over 40 different printers are supported.  To print Gantt
  185.           charts using graphic characters, your printer must support
  186.           the I.B.M. character set.
  187.  
  188.      Software
  189.           DOS 2.x or 3.x
  190.           CONFIG.SYS File
  191.                A CONFIG.SYS file must be in the root directory of the
  192.                boot disk.  This file should contain the following two
  193.                records:
  194.                     BUFFERS = 24
  195.                     FILES = 24
  196.                These values are minimum values.
  197.                Re-boot DOS after making these changes.
  198.  
  199.  
  200.                                Installation
  201.  
  202.      Hard Disk
  203.           To install Easy Project on a hard disk system, place your copy
  204.           of Easy Project in drive A and type:
  205.                        INSTALLH
  206.  
  207.           This installation procedure will create a sub-directory on
  208.           your hard disk of \EP and copy the necessary files.
  209.  
  210.      2 Floppy System
  211.  
  212.           1.  Make a backup of your Easy Project disk.
  213.           2.  Using backup copy in drive A and blank formatted disk
  214.               in drive B, type:  INSTALLF <enter>
  215.  
  216.               This process will copy all necessary data files to drive
  217.               B and keep system files on drive A.  Label the disk in
  218.               drive A "EP System" and the disk in drive B "EP Data".
  219.  
  220.  
  221.  
  222.  
  223.                        E A S Y  P R O J E C T  (tm)
  224.  
  225.  
  226.                            Starting Easy Project
  227.  
  228.      Hard Disk
  229.  
  230.           From the \EP directory, type:  EP <enter>
  231.  
  232.      2 Floppy System
  233.  
  234.          With the EP System disk in drive A and the EP Data disk
  235.          in drive B, type :  EP <enter>
  236.  
  237.  
  238.  
  239.  
  240.      NOTE:  The first time you execute Easy Project, choose the
  241.             Utilities option from the Main Menu.  From this menu,
  242.             configure both your monitor and your printer.  After
  243.             making your monitor and printer choices, exit the system
  244.             and re-enter to have the monitor configuration take effect.
  245.  
  246.  
  247.  
  248.  
  249.  
  250.  
  251.  
  252.                        E A S Y  P R O J E C T  (tm)
  253.  
  254.  
  255.  
  256.                              Data Entry Notes
  257.  
  258.  
  259.        On all Easy Project screens and menus, the cursor can be controlled 
  260.        in the following fashion:
  261.  
  262.     Key                         Result
  263.  
  264. <--|  (Enter)          Proceeds to the next field.  When
  265.                        pressed while the cursor is in the
  266.                        last field of a screen or menu, all
  267.                        data will be saved.
  268.  
  269. PgDn                   Exits the screen saving all changes.
  270.  
  271. Esc                    Exits the screen without saving any
  272.                        changes.
  273.  
  274. Up Arrow               Moves cursor to previous field.
  275.  
  276. Down Arrow             Moves cursor to next field.
  277.  
  278. <-                     Moves cursor backward one space.
  279.  
  280.  ->                    Moves cursor forward one space.
  281.  
  282. F5                     Deletes record while in Resource or
  283.                                     Task update screens.
  284.  
  285. F1                     At any time while in Easy Project,
  286.                                     help is available by pressing 'F1'.
  287.                                     Easy Project will recognize what field
  288.                                     or menu the request came from, and
  289.                                     then display the appropriate text.
  290.  
  291.      Three heavily used fields will provide additional HELP when F1 is
  292.      prossed:
  293.  
  294.           Project Number:  Will list all current projects on file.
  295.  
  296.           Task Number:     Will list all current tasks for a particular
  297.                            project.
  298.  
  299.           Resource:        Will list all current resources for a
  300.                            particular project.
  301.  
  302.  
  303.  
  304.  
  305.                        E A S Y  P R O J E C T  (tm)
  306.  
  307.  
  308.                                  Main Menu
  309.  
  310.  
  311.      The Main Menu is the driver for Easy Project.  On this and all
  312.      other menus, enter the number choice for the function you want.
  313.  
  314.  
  315.      The components of the Main Menu are:
  316.  
  317.               Set Up Project Parameters
  318.               Used to create project numbers, project descriptions,
  319.               phase descriptions and set Gantt scales.
  320.  
  321.               Add/Change/Delete Resources
  322.               Used for adding and maintaining resource data.
  323.  
  324.               Add/Change/Delete Tasks
  325.               Used for adding and maintaining task detail data.
  326.  
  327.               Automatic Schedule Generation
  328.               Schedule work plans automatically.
  329.  
  330.               Gantt Charts
  331.               Produce Gantt charts for a project or phase showing
  332.               original vs. current task dates.
  333.  
  334.               Reports
  335.               Generate nine different reports including work plans,
  336.               status reports and summary reports.  This function contains
  337.               its own menu.
  338.  
  339.               Utilities
  340.               Used to configure system and provide sundry utility
  341.               file handling.  This function contains its own menu.
  342.  
  343.               Registration Information
  344.               How to register Easy Project.
  345.  
  346.               Exit to DOS
  347.               Return to operation system.
  348.  
  349.  
  350.  
  351.  
  352.  
  353.  
  354.                        E A S Y  P R O J E C T  (tm)
  355.  
  356.  
  357.                           Creating a New Project
  358.  
  359.  
  360.        Easy Project is designed for quick project creation.  After
  361.        spending a short time entering project data, Gantt charts and
  362.        reports will become available.
  363.  
  364.        Follow this process when creating a new project:
  365.  
  366.            1.  Choose 'Set Up Project Parameters' from the Main Menu and
  367.                enter project number, descriptions, phase descriptions and
  368.                appropriate Gantt scale information.
  369.  
  370.            2.  Choose 'Add/Change/Delete Resources' from the Main Menu and
  371.                add resource data for the project.  Resources will be
  372.                identified by assigning them a unique user defined code.
  373.  
  374.            3.  Choose 'Add/Change/Delete Tasks' from the Main Menu to
  375.                enter individual tasks to the project. (See Notes On
  376.                Entering Tasks)
  377.  
  378.            4.  If you want Easy Project to calculate estimated schedule
  379.                dates, choose 'Automatic Schedule Generation' from the Main
  380.                Menu. (See Notes on Automatic Scheduling)
  381.  
  382.            5.  At this point, Gantt charts and/or reports may be produced.
  383.  
  384.  
  385.  
  386.  
  387.  
  388.                        E A S Y  P R O J E C T  (tm)
  389.  
  390.  
  391.                          Set Up Project Parameters
  392.  
  393.        Easy Project has the ability to store data from several different
  394.        projects at one time.  Each of those projects can have different base
  395.        parameters.
  396.  
  397.        Before task or resource data can be entered for a particular
  398.        project, certain parameters or criteria must be defined.
  399.  
  400. Project Number
  401.  
  402.              Every project must have its own unique project number.  This
  403.              number is used to tell the system what project should be
  404.              retrieved.  This number can be composed of any combinations of 
  405.              characters or numbers (5 character maximum).
  406.  
  407.              NOTE:  Pressing 'F1' while on the project number field will 
  408.              provide a list of all currently used numbers.
  409.  
  410. Project Name
  411.  
  412.              The Project Name is used to identify the project.  This 
  413.              description will appear on all screens and reports.
  414.  
  415. Project Description
  416.  
  417.              To further define a project, use these fields.  The data 
  418.              entered here will print on all reports.
  419.  
  420. Phase Descriptions
  421.  
  422.              For most projects, it is better to divide the project into
  423.              smaller, more manageable phases.  Examples of phases could be:
  424.  
  425.                   1.  Lay foundation
  426.                   2.  Framing
  427.                   3.  Plumbing
  428.                         OR
  429.                   1.  Feasibility Study
  430.                   2.  Design and Analysis
  431.                   3.  Programming
  432.                   4.  Acceptance
  433.  
  434.              Easy Project permits 20 different phases to be defined for one
  435.              particular project.  The descriptions entered here will appear 
  436.              on project summary reports.
  437.  
  438. Gantt Scale
  439.  
  440.              Flexible Gantt scales can be chosen to insure the most
  441.              complete view of a project.  Each symbol on the chart can 
  442.              represent from 1 to 6 days or weeks.  For projects of short 
  443.              duration, a scale in days is probably more appropriate.
  444.  
  445.  
  446.  
  447.                        E A S Y  P R O J E C T  (tm)
  448.  
  449.  
  450.                         Add/Change/Delete Resources
  451.  
  452.  
  453.  
  454.        Before task data can be entered, resource information must be 
  455.        established.  Resources may consist of human type
  456.        (employees, consultants, etc.) or fixed type (materials, capital
  457.        expenses, etc.).
  458.  
  459.  
  460. Field Descriptions
  461.  
  462. Identifier:  Each resource must be assigned a unique
  463.              identifier.  This identifier could be a name,
  464.              initials or an account code.  The identifier
  465.              can be up to 6 characters and is alphanumeric.
  466.  
  467.              NOTE:  Pressing F1 while the cursor is in the
  468.                     Identifier field will produce a list of
  469.                     all resources already assigned to the project.
  470.  
  471. Name:        Enter the full name or description of the
  472.              resource.
  473.  
  474. Rate:        The charge rate for the resource.
  475.  
  476. Type:        Choose either Hourly, Daily, or Fixed. If
  477.              Fixed is chosen, this resource will not be
  478.              automatically scheduled.
  479.  
  480. Dept:        Enter a department code for the resource.  This
  481.              code may be up to 3 characters and is
  482.              alphanumeric.
  483.              NOTE:  This is an optional entry but is required
  484.                     to produce departmentalized reports.
  485.  
  486. Useage:      Used to identify how many hours this resource
  487.              works in one day.  (not needed for Fixed types)
  488.  
  489. Source:      An optional entry to further describe the
  490.              resource.
  491.                 Example:  EMP = Employee
  492.                           CON = Consultant
  493.  
  494. Note 1 &
  495. Note 2:      An optional entry to use for any purpose.
  496.  
  497.  
  498.  
  499.                           E A S Y  P R O J E C T
  500.  
  501.  
  502.                           Add/Change/Delete Tasks
  503.  
  504.  
  505.        Task definition is the heart of project management.  Easy Project 
  506.        permits for practical task creation and maintenance.  Before sitting 
  507.        down and entering data, plan what logical order your tasks will
  508.        follow and if possible, divide your project into phases.  Once your 
  509.        data has been entered, refinement and maintenance is easy.
  510.  
  511. Field Definitions
  512.  
  513. Task:                  Enter the two digit phase number plus
  514.                        three digit task number for this task.
  515.                        Refer to 'Notes on Entering Tasks' for
  516.                        choosing task numbers.
  517.  
  518. Item:                  Each task can consist of numerous
  519.                        subordinate tasks or items.  Enter an
  520.                        item number in this field. (optional)
  521.  
  522. Predecessor:           Use this field to tie tasks to a
  523.                        proceeding or parent task.  Refer to
  524.                        'Assigning Predecessors'.
  525.  
  526. Description:           Enter the description for this task.
  527.                        This description will appear on all
  528.                        reports and Gantt charts.
  529.  
  530.    Milestone:          If this task in considered a Milestone
  531.                        in the project, enter 'Y'.
  532.  
  533. Resource:              Enter the resource identifier of the
  534.                        resource assigned to this task.  A
  535.                        maximum of four different resources
  536.                        may be assigned to a particular task.
  537.  
  538. Est. Time:             Enter the amount of time (hours/days)
  539.                        this task is expected to take to
  540.                        complete this task.
  541.  
  542. Time To-Date:          Enter the amount of time this resource
  543.                        has taken thus far for this task.
  544.  
  545. Original Start/Stop:   Enter the original or planned start
  546.                        and stop date for this task.
  547.  
  548. Current Start/Stop:    Enter the current start and stop date
  549.                        for this task.
  550.  
  551. Note 1 & Note 2:       To be used for any purpose.
  552.  
  553. Remaining:             Enter the time remaining for this
  554.                        task.  The system will default to
  555.                        the difference between estimated and
  556.                        time to-date.
  557.  
  558.  
  559.  
  560.  
  561.                        E A S Y  P R O J E C T  (tm)
  562.  
  563.  
  564. Notes on Entering Tasks
  565.  
  566. Every task number consists of the following elements:
  567.                 Task Number  - 2 character phase number (01-20) plus
  568.                                3 character task number (user defined)
  569.                 Item Number  - 2 characters, user defined (optional)
  570.                 Predecessor  - 7 characters, made up of (Phase + Task +
  571.                                Item)
  572.  
  573.              Keep in mind that most reports are produced in task number 
  574.              order. Using sequential task numbers of 001, 002, etc. within 
  575.              each phase is recommended.
  576.  
  577.              Item number is meant as a subordinate task.  This is an
  578.              optional entry but is useful in breaking down a large main 
  579.              task.  Again, it's useful to use sequential item numbers 
  580.              within each task number.
  581.  
  582.              Predecessor designates what task, if any, the current task is 
  583.              dependent upon.  This field is also optional and will default 
  584.              to its own task and item number.  If this is used, it should 
  585.              consist of the phase, task and item number of the preceding 
  586.              task.
  587.  
  588. Assigning Predecessors
  589.  
  590.              Predecessor numbers should be assigned using the parent or 
  591.              host task number.  Several tasks can all contain the same
  592.              predecessor number.  If no predecessor is assigned, the system 
  593.              will default to the task number.
  594.  
  595.    Sample Task Numbers
  596.  
  597.           Task Field  =  01-002
  598.           Item Field  =  03
  599.           Predecessor =  01-002 03
  600.           Definition:  This task belongs to phase 1, task equals 002 and
  601.                        this is the third item for task 002.
  602.                        This task is not dependent on any other task so the
  603.                        predecessor field defaults to the phase, task and
  604.                        item number.
  605.  
  606.           Task Field  = 01-003
  607.           Item Field  = 01
  608.           Predecessor = 01-002 03
  609.  
  610.           Definition:  This task belongs to phase 1, task equals 003 and
  611.                        this is the first item for task 003.
  612.                        This task is dependent on the task from the first
  613.                        example (its parent task).
  614.  
  615.  
  616.  
  617.                           E A S Y  P R O J E C T
  618.  
  619.  
  620. Automatic Schedule Maintenance
  621.  
  622.              If an original start or stop date is changed, for an existing 
  623.              task, the automatic scheduler will be invoked adjusting both 
  624.              original and current start/stop dates.  This adjustment will 
  625.              occur only for tasks assigned the same predecessor.  You will 
  626.              have the ability to override the proposed dates.
  627.  
  628.              Likewise, if a current start or stop date is changed, the 
  629.              automatic scheduler will be invoked to adjust current dates 
  630.              only.
  631.  
  632. Marking Tasks Complete
  633.  
  634.              For the purpose of the Project Status Report, Easy Project 
  635.              considers a task complete when time remaining equals zero and 
  636.              estimated or time to-date is greater than zero.
  637.  
  638.  
  639.  
  640.                        E A S Y  P R O J E C T  (tm)
  641.  
  642.  
  643.                        Automatic Schedule Generation
  644.  
  645.  
  646.        Easy Project will automatically calculate original start and stop
  647.        dates based on the estimated time assigned to each task.
  648.  
  649.        To calculate dates, enter the project number followed by the base
  650.        start date.  The base start date should be the date the project may
  651.        begin.
  652.  
  653.  
  654.      Schedule Screen Display
  655.  
  656.        As the schedule generates, each task and the newly calculated dates
  657.        are displayed.  After the screen fills, you have the ability
  658.        to change or override the calculated date.  Pressing <ESC> aborts
  659.        the update process and the records will not be updated.
  660.  
  661.        Use the <ENTER> key to advance the cursor.  When the screen
  662.        is completely updated, these dates will be used to update both the
  663.        original and the current start and stop dates for the tasks.
  664.  
  665.  
  666.       Notes on Dependencies
  667.  
  668.        For automatic scheduling and Gantt charts, dependencies should be
  669.        created using the following example:
  670.  
  671.              In the case of tasks 001, 002, 003 and 004 being dependent
  672.              upon the respective prior task (004 on 003, 003 on 002, etc.)
  673.              assign tasks 002, 003, and 004 dependent to task 001.
  674.  
  675.              Think of task 001 as the parent task and then place the
  676.              dependent tasks in task number order.
  677.  
  678. Notes on Scheduling
  679.  
  680.              1.  In the case of multiple resource tasks, the resource
  681.                  taking the greatest amount of time will be used in
  682.                  calculating the schedule. (the display reflects this)
  683.  
  684.              2.  Any task which has a fixed type resource will be ignored.
  685.  
  686.              3.  On the Resource update screen, the Useage field should
  687.                  reflect the total number of hours the resource works
  688.                  in one day. Use this for both hourly and daily type
  689.                  resources.
  690.  
  691.              4.  Weekends will be taken into consideration when
  692.                  calculating the schedule.
  693.  
  694.  
  695.  
  696.  
  697.                         E A S Y  P R O J E C T  (tm)
  698.  
  699.  
  700.                                 Gantt Chart
  701.  
  702.        Easy Project's Gantt charts are designed to give a graphic display 
  703.        of a projects planned vs. actual progress.
  704.  
  705.        Two different types of charts may be produced:
  706.  
  707.              1.  A chart displaying task for one particular phase in
  708.                  task number order.
  709.  
  710.              2.  A chart displaying the entire project with tasks grouped
  711.                  by dependencies.
  712.  
  713.        In order for a task to be displayed, it must have an Original Start
  714.        Date.
  715.  
  716.  
  717.     Scale Options
  718.  
  719.        Refer to Set Up Project Parameters on how to set the Gantt scale.  
  720.        It may be changed at any time during the project.
  721.  
  722.  
  723. Output Options
  724.  
  725. Easy Project offers three options for generating Gantt charts:
  726.  
  727.           1.  (D)isplay - The chart will be displayed on your monitor.
  728.                           If the scale is set to 1 day, a view of
  729.                           2 months will be displayed.
  730.  
  731.           2.  (P)rint - The chart will be printed in compressed format.
  732.                         With a scale set to 1 day, a view of approximately
  733.                         4 months will be printed.
  734.  
  735.           3.  (F)ile -  The chart will be written to a disk file named
  736.                         GANTT.PRN.  This is an ASCII file that may be
  737.                         printed through DOS or by using another print
  738.                         utility program.  If the scale is set to 1 day,
  739.                         a view of approximately 6 months will be printed.
  740.  
  741.  
  742.  
  743.  
  744.                        E A S Y  P R O J E C T  (tm)
  745.  
  746.  
  747.                                 Report Menu
  748.  
  749.  
  750.        Many helpful reports can be instantly generated either online or 
  751.        sent to your printer.  Due to space limitations, some reports are 
  752.        printed in compressed format - thus giving more detail than when 
  753.        displayed online.
  754.  
  755.        Sample copies of all reports are contained at the end of this 
  756.        manual.
  757.  
  758.               Work Plan By Task - Produces a detailed work plan for
  759.               a particular phase in task number order.
  760.  
  761.               Work Plan By Resource - Produces a detailed work plan for
  762.               the entire project in order of task original start date
  763.               within resource.
  764.  
  765.               Work Plan Project Summary - Summarizes all phases of a
  766.               project plan giving a concise report.
  767.  
  768.               Work Plan Resource Summary - Produces a departmentalized
  769.               resource summary either for a particular phase or the entire
  770.               project.
  771.  
  772.               Project Status Report (Plan vs. Actual) - A to-date status
  773.               report for the entire project.
  774.  
  775.               Project Status Summary (Actual) - Summarizes all project
  776.               phases showing actual costs and current dates.
  777.  
  778.               Project Resource Summary (Actual) - Shows departmental
  779.               break down of actual costs by individual resource.
  780.  
  781.               Earned Value Report - A to-date report detailing cost
  782.               accruals.
  783.  
  784.               Resource List - Gives a detailed list of all resources
  785.               assigned to a particular project.
  786.  
  787.               Exit - Return to the Main Menu.
  788.  
  789.  
  790.  
  791.  
  792.  
  793.                            E A S Y  P R O J E C T  (tm)
  794.  
  795.  
  796.  
  797.                                 Utility Menu
  798.  
  799.  
  800.     The Utility Menu consists of various functions that may be used for
  801.     file handling or system configuration.
  802.  
  803.     NOTE:  Be sure to backup all Easy Project files on a regular basis.  
  804.            This will help in recovering from any potential disasters.
  805.  
  806.  
  807. Reindex All Files
  808.  
  809.              Easy Project uses several index files which permits fast data
  810.              retrieval.  These index files are not compatible with dBASE or
  811.              any other known applications.  All files with the extension of
  812.              .NTX should never be deleted.
  813.  
  814.              If the file integrity of your files is every in question,
  815.              choose the reindex option.  File integrity may degrade due to
  816.              abnormal termination of the system.
  817.  
  818.              It can never hurt the system to reindex files.
  819.  
  820.  
  821. Delete (Pack) Marked Records
  822.  
  823.              When task or resource data is deleted using the 'F5' key, 
  824.              they (records) are actually marked for deletion but physically 
  825.              remain on file.  These records are unavailable for normal use.
  826.  
  827.              The delete option on this menu will physically delete all 
  828.              marked records.  Once this option is exercised, the marked 
  829.              records can no longer be used or recovered.
  830.  
  831.  
  832. Undelete (Recall) Records
  833.  
  834.              This option will seek all records that have been marked for 
  835.              deletion (and not packed), and recall or make them available 
  836.              again for processing.
  837.  
  838.              NOTE:  This option will recall all records from all project 
  839.              from all files regardless of project number.
  840.  
  841.  
  842.  
  843.  
  844.                        E A S Y  P R O J E C T  (tm)
  845.  
  846.  
  847.                          Utility Menu (continued)
  848.  
  849.  
  850. Delete Project
  851.  
  852.              This function will delete all tasks, resources and related 
  853.              records for a particular project.
  854.  
  855.              To use, first enter the project number to delete.  Next, you 
  856.              will be prompted to verify that you really want to delete the 
  857.              project.  Answering 'N' will bypass any deletions.  If 
  858.              verified, records are marked for deletion.
  859.  
  860.  
  861. Copy or Clone Project
  862.  
  863.              On occasion, you may want to create a project that has many 
  864.              similar tasks as another project previously entered.  The copy
  865.              option will take a current project and duplicate all tasks and 
  866.              resources using a new project number.  The old project remains 
  867.              intact with no changes.  
  868.  
  869.  
  870. Rebuild Files from Importing
  871.  
  872.              Easy Project database files (.DBF) are dBASE III compatible 
  873.              and can be exported directly into many other applications.  
  874.              Exporting may provide useful for additional reporting or mass 
  875.              updating.
  876.  
  877.              If files are exported and then imported into Easy Project, 
  878.              they must be rebuilt.  This function will automatically 
  879.              rebuild index files and all necessary relations.
  880.  
  881.              NOTE:  Exercise caution when updating Easy Project files from 
  882.              outside applications.  Be sure to have recent backups of all
  883.              files as a safeguard.
  884.  
  885.  
  886. Backup Data Files
  887.  
  888.              On a regular, consistent basis, backups should be made of 
  889.              Easy Project files.  This option will copy all databases 
  890.              (.DBF) to a floppy disk.  If you are using a two floppy 
  891.              system, use drive A:
  892.  
  893.              NOTE:  This function copies only data files.  Regular backups 
  894.              of all Easy Project files should be made using the DOS COPY or 
  895.              DISKCOPY commands.
  896.  
  897.              If files are used from a backup, be sure to reindex the 
  898.              files.
  899.  
  900.  
  901.  
  902.  
  903.                            E A S Y  P R O J E C T  (tm)
  904.  
  905.  
  906.  
  907.                          Utility Menu (continued)
  908.  
  909.  
  910. Configure Monitor
  911.  
  912.              This option sets the proper type of monitor for your system.  
  913.              To have these changes take effect, exit Easy Project 
  914.              completely and then re-enter.
  915.  
  916.  
  917. Configure Printer
  918.  
  919.              Easy Project supports many printers.  Find the number that 
  920.              corresponds to your printer and enter the number at the 
  921.              prompt.  If your printer is not listed, choose either the 
  922.              I.B.M. Graphics or Other ASCII Printer.
  923.  
  924.              To print Gantt charts using the same graphic characters that
  925.              are displayed, your printer must support the I.B.M. character 
  926.              set.
  927.  
  928.  
  929. Exit
  930.  
  931. This will return you to the Main Menu.
  932.  
  933.  
  934.  
  935.  
  936.                        E A S Y  P R O J E C T  (tm)
  937.  
  938.  
  939.                                 Conclusion
  940.  
  941.  
  942.      We hope this User Guide assists in your using Easy Project.
  943.  
  944.      Easy Project is a dynamic system that will constantly be upgraded
  945.      and improved.  Your suggestions and comments are greatly appreciated.
  946.  
  947.      If you have any questions about Easy Project, please contact us
  948.      by mail or via CompuServe EasyPlex.
  949.  
  950.      Please remember to register if you find yourself using Easy Project.
  951.      Registered users will receive:
  952.  
  953.              1.  Latest version of Easy Project with Shareware screen
  954.                  disabled
  955.  
  956.              2.  Printed User Guide with sample screens, reports and
  957.                  Gantt charts 
  958.  
  959.              3.  Notification of updates
  960.  
  961.              4.  Free technical support
  962.  
  963.      Thanks again for using Easy Project.
  964.  
  965.  
  966.  
  967.                              Parcell Software
  968.                            948 Manchester Course
  969.                              Geneva, Il  60134
  970.                               (312) 232-6328
  971.  
  972.                         CompuServe ID (72250,1356)