John Soyring Comments on Warp Production and Availability
October 27, 1994
The following is the body of a letter that was fax'ed earlier this
week to senior executives of PC companies. It is also being sent
to others worldwide.
Today, I have received many notes stating that they
admire that we are being forthright, and they applaud
the action IBM has taken to fix even a minor problem.
These people have encouraged me to post the body
of the letter on public BBS's.
I hope that this information helps others understand what
happened and what we are doing. We are confident that
once people try Warp, they will find it to be a high quality
product and a great value.
********************************************************
Dear ________:
This week there will be articles or columns in both business
press and trade press publications that may cause you some
degree of concern about the quality of the new OS/2 Warp
product that we announced on October 11. We have also been
told that someone is calling companies in the personal computer
industry to tell senior executives that "IBM has stopped production
of Warp" and that a "myriad of problems" exist in Warp.
I would like to share with you exactly what has happened, and
what will be happening.
The bottom line is: the product has successfully completed
all of our quality assurance testing; the product is being
manufactured; we plan to have it available on store shelves
this coming week; and PC manufacturers will start preloading
and shipping to their customers as early as today.
The final testing of Warp included a massive, public beta test (two
cycles) during which tens of thousands of users, ISV's, OEM's, and
others tested Warp for months. We then conducted a gamma test on
a smaller scale with a representative cross section of users and
vendors. This was all in addition to our internal testing. The final
test results were excellent.
Once the gamma test completed, we began manufacturing Warp,
shipping initial shrinkwrap products to members of the press,
consultants and distributing it widely within IBM.
In our on-going quality testing, we discovered a minor problem. We
quickly analyzed the problem and determined the cause. Though this
bug would have affected only a small number of users, we decided to
stop the manufacturing of Warp and fix the problem now before Warp
was widely distributed in reseller channels. We want to ensure that
all of our customers have a good experience with the new Warp product.
Our media relations team received the first boxes off the line to
send to reviewers, one of whom was Mike Putzer of the Boston Globe.
He experienced the problem and, after we called him with the fix,
he decided to write the story of our decision to restart manufacturing
to include the fix. The article appeared in the October 26 issue,
with the headline "IBM Halts Warp Production."
There is some product already in the distribution channel, but the
bulk of manufactured product went internally to IBM. Those boxes
that are in the channel will be immediately replaced with boxes with
the new code. Any customers that have purchased the product, and
have the installation problem, will be helped with the simple
correction, with guidance provided by the IBM customer support staff.
We will also replace purchased copies, if the customer wishes.
OS/2 Warp will be initially available in the channel next week and
widely available by November 4. IBM is confident that users will be
delighted with the performance and impressive new features of Warp.
And we are absolutely committed to delivering the highest quality
product, which is why we made the decision to fix the problem now.
I hope this information helps. Please let me know if you would like
additional details.
Sincerely,
John A. Soyring
Division Director
IBM Personal Software Products Division
************************************************************************