home *** CD-ROM | disk | FTP | other *** search
/ Internet Standards / CD2.mdf / ccitt / 1992 / q / q709.asc < prev    next >
Text File  |  1991-12-31  |  35KB  |  712 lines

  1.          All drawings appearing in this Fascicle have been done in Autocad.
  2.          Recommendation Q.709
  3.                      HYPOTHETICAL SIGNALLING REFERENCE CONNECTION
  4.          1      Introduction
  5.                This Recommendation specifies how the elements of a  signalling  connection
  6.          are combined to  meet  the  signalling  requirements  of  the  networks  that  it
  7.          supports. Included are parameters for signalling transfer delay in both  national
  8.          and international networks, and overall signalling delay that  such  combinations
  9.          will produce, together with the availability required, to enable the  performance
  10.          of the network served by the signalling network to be maintained.
  11.                A probabilistic approach is been taken,  i.e.,  limits  are  specified  for
  12.          mean and 95% of connections. These figures will apply to the normal operation  of
  13.          a  signalling  network.  No  consideration  is  given  to  the  "unusually  long"
  14.          signalling paths that are found in some signalling networks. Any unusual  routing
  15.          caused by some network structures and/or reconfigurations due to network  failure
  16.          are considered to be covered in the remaining 5% of connections.
  17.                The hypothetical signalling reference connection (HSRC)  for  international
  18.          working is specified in this Recommendation by defining the constituent parts of:
  19.                i)  the international section,
  20.                ii) the national section.
  21.                In any combination of those sections to  produce  an  overall  hypothetical
  22.          signalling reference connection, it is necessary to consider what impact each  of
  23.          the component parts (international and two national sections) have on each  other
  24.          and the full  hypothetical  signalling  reference  connection.  This  means  that
  25.          certain national or international limits such as the maximum number of signalling
  26.          transfer points allowed in a signalling relation  (see  Recommendation  Q.705,  S
  27.          5.2)  require  modification  and  account  of  this  has  been  taken   in   this
  28.          Recommendation.
  29.          2      Requirements of networks served by the signalling connection
  30.                To meet the requirements of services carried on the network served  by  the
  31.          signalling network, the  signalling  connection  performance  should  be  closely
  32.          aligned with those requirements.  Since  these  services  are  ultimately  to  be
  33.          carried on an ISDN, the hypothetical signalling  reference  connection  is  based
  34.          upon  the  hypothetical  reference   connection   produced   for   that   network
  35.          (Recommendation G.801).
  36.                However, for a considerable time the majority of services  in  the  network
  37.          served by the  signalling  network  will  be  telephony-based  and  account  must
  38.          therefore be  taken  of  the  reference  connection  for  conventional  telephony
  39.          application (Recommendation G.101).
  40.          3      Hypothetical signalling reference connection components for 
  41.                link-by-link signalling
  42.          3.1    General
  43.                The components of  an  hypothetical  signalling  reference  connection  are
  44.          signalling points and STPs which are connected in series by signalling data links
  45.          to produce a signalling connection (Note 1). The number of signalling points  and
  46.          STPs depend on the size of the network. Two limits are prescribed to  cover  mean
  47.          or 95% cases. Separate cases are allowed for large countries  and  average  sized
  48.          countries  (Note  2).  This  section  outlines  the  considerations  involved  in
  49.          formulating a  hypothetical  signalling  reference  connection  for  link-by-link
  50.          signalling and details the number of hypothetical signalling reference connection
  51.          components and the delays they produce.
  52.                Note 1 - The term signalling point is used to designate  use  of  the  user
  53.          function in a  signalling  point:  whether  or  not  STP  function  is  presented
  54.          irrelevant in this context. The term STP is used to  designate  use  of  the  STP
  55.          function in a signalling point: whether  or  not  user  function  is  present  is
  56.          irrelevant in this context.
  57.  
  58.  
  59.  
  60.  
  61.  
  62.  
  63.  
  64.  
  65.  
  66.  
  67.  
  68.  
  69.  
  70.                                                         Fascicle VI.7 - Rec. Q.709   PAGE1
  71.  
  72.                 Note 2 - When the  maximum  distance  between  an  international  switching
  73.           centre and a subscriber who can be reached from it does not exceed  1000  km  or,
  74.           exceptionally, 1500 km, and when the country has less than n x  107  subscribers,
  75.           the country is considered as of average size. A country with  a  larger  distance
  76.           between an international switching centre and a subscriber, or with more than n x
  77.           107 subscribers, is considered as of large size. (The value of n is  for  further
  78.           study.)
  79.           3.1.1  Number of signalling  points  in  the  hypothetical  signalling  reference
  80.                  connection
  81.                 The number of signalling points in the  hypothetical  signalling  reference
  82.           connection has been determined by considering the maximum number of links allowed
  83.           by the Telephone Routing Plan (Q.13/E.171). These  Recommendations  define  "last
  84.           choice" backbone routes and only a small proportion of traffic take these routes.
  85.           Traffic generated in metropolitan areas, generally the largest source of traffic,
  86.           usually takes far fewer links to an  international  switching  centre.  Even  for
  87.           rural areas a connection to the international switching centre will not generally
  88.           be required to follow the backbone route.
  89.                 Limitation of the number of signalling  points  required  will  reduce  the
  90.           signalling delay, considering that signalling  point  delay,  forms  the  largest
  91.           component of signalling delay.
  92.           3.1.2  Number of STPs in an hypothetical signalling reference connection
  93.                 The number of STPs in the hypothetical signalling reference  connection  is
  94.           a function of the  number  of  signalling  points,  and  the  signalling  network
  95.           topology used to connect these signalling points. The number of  STPs  should  be
  96.           kept to a minimum in order to limit the  signalling  delay.  In  some  signalling
  97.           relationship, associated signalling may be used for which no STPs  are  required.
  98.           In  others,  one  or  more  STPs  may  be  used.  For  international   signalling
  99.           relationship, it is recommended that no more than 2 STPs be used in a  signalling
  100.           relation. (See Recommendation Q.705, S 5.2.)
  101.           3.1.3  Signalling network availability
  102.                 The availability  of  a  signalling  connection  is  an  important  network
  103.           parameter. It is necessary for the availability to be significantly  better  than
  104.           the availability of the component being controlled (e.g. a circuit). A figure  of
  105.           10 minutes down time per year  maximum  unavailability  is  recommended  for  any
  106.           particular signalling route set (Recommendation Q.706, S 1.1).
  107.                 This corresponds to an availability of 0.99998, which can  be  achieved  by
  108.           the use of suitable network redundancies.
  109.           3.1.4  Signalling message transfer delay
  110.                 Signalling message transfer delay is another important  network  parameter.
  111.           It affects call set up delay and also affects network response  time  to  service
  112.           requests made during a call. In this Recommendation, the transmission propagation
  113.           delays are not included (see S 7.2).
  114.           3.2    International component of hypothetical signalling reference connection
  115.                 The  international  component  of  the  hypothetical  signalling  reference
  116.           connection includes all international signalling points in the connection and the
  117.           STPs carrying signalling messages between  the  signalling  points.  The  maximum
  118.           number of signalling points and STPs allowed are listed in Table 1/Q.709.
  119.                 The  unavailability  of  the  overall  international   component   of   the
  120.           signalling network should not exceed the following totals per year for  both  the
  121.           50 and 95 percent cases.
  122.                  -   20 minutes for large country to large country,
  123.                  -   30 minutes for large country to average-sized country, and
  124.                  -   40 minutes per year for average-sized country to average-sized country.
  125.                                                  TABLE 1/Q.709
  126.                     Maximum number of signalling points and STPs in international component
  127.               Country size (Note)       Percent of      Number of       Number of 
  128.                                         connections        STPs        signalling 
  129.                                                                            points
  130.           Large                            mean             3        
  131.           to                                                                 3
  132.           Large                              95              4        
  133.           Large                            mean             4         
  134.           to                                                                 4
  135.           Average-sized                      95              4        
  136.           Average-sized                    mean             5        
  137.           to                                                                 5
  138.           Average-sized                      95              7        
  139.  
  140.  
  141.  
  142.           PAGE1   Fascicle VI.7 - Rec. Q.709
  143.  
  144.                 Note See Note 2 to S 3.1.
  145.                 The maximum signalling transfer  delay  under  normal  conditions  for  the
  146.           international component of a connection should  not  be  worse  than  the  values
  147.           listed in Table 2/Q.709.
  148.           3.3    National components of hypothetical signalling reference connection
  149.                 The  national  components  of   the   hypothetical   signalling   reference
  150.           connection includes all national  exchanges  in  the  connection  (but  does  not
  151.           include the international switching centre in the country) and all STPs  carrying
  152.           signalling messages between the national exchanges and between the highest  level
  153.           national exchange and the international switching centre. The maximum  number  of
  154.           signalling points and STPs allowed are listed in Table 3/Q.709.
  155.  
  156.                                                  TABLE 2/Q.709
  157.                              Maximum signalling delays for international component
  158.                                                              Delay (Note) (ms)
  159.                 Country size         Percent of              Message type
  160.                                       connections   
  161.                                                         Simple         Processing 
  162.                                                      (e.g. answer)     intensive 
  163.                                                                         (e.g. IAM)
  164.           Large                          mean            390             600 
  165.           to                                                         
  166.           Large                            95             410              620
  167.           Large                           mean            520              800 
  168.           to                                                         
  169.           Average-sized                    95             540              820
  170.           Average-sized                  mean            650             1000 
  171.           to                                                         
  172.           Average-sized                    95             690             1040
  173.                 Note - Only the mean delay component from Table 4/Q.706, Table 3/Q.725 and 
  174.                 Table 1/Q.766 have been used in calculating the delay. Further study is 
  175.                 required, e.g. for the mean values as well as the inclusion of overload 
  176.                 and/or 95 percentile cases of each component value.
  177.  
  178.  
  179.  
  180.  
  181.  
  182.  
  183.  
  184.  
  185.  
  186.  
  187.  
  188.  
  189.  
  190.  
  191.  
  192.  
  193.  
  194.  
  195.  
  196.  
  197.  
  198.  
  199.  
  200.  
  201.  
  202.  
  203.  
  204.  
  205.  
  206.  
  207.  
  208.  
  209.  
  210.  
  211.  
  212.  
  213.                                                          Fascicle VI.7 - Rec. Q.709   PAGE1
  214.  
  215.                                                 TABLE 3/Q.709
  216.                      Maximum number of signalling points and STPs in national components
  217.             Country size (Note 1)      Percent of      Number of       Number of 
  218.                                        connections        STPs        signalling 
  219.                                                                           points
  220.                                            mean             3              3
  221.          Large                                                        
  222.                                             95              4              4
  223.                                            mean             2              2
  224.          Average-sized                                                
  225.                                             95              3              3
  226.               Note 1 - See Note 2 to S 3.1.
  227.               Note 2 - The values in this Table are provisional. (A higher number of 
  228.               signalling points and/or STPs might be included in a national network, 
  229.               e.g. in the case that a two-level hierarchical signalling network is 
  230.               adopted. This matter is for further study.)
  231.                The unavailability of each  of  the  overall  national  components  of  the
  232.          signalling network should not exceed the following totals per year:
  233.                -   20 minutes for mean case of average-sized countries,
  234.                -   30 minutes for 95 percent case of average-sized countries and mean case 
  235.  
  236.  
  237.  
  238.  
  239.  
  240.  
  241.  
  242.  
  243.  
  244.  
  245.  
  246.  
  247.  
  248.  
  249.  
  250.  
  251.  
  252.  
  253.  
  254.  
  255.  
  256.  
  257.  
  258.  
  259.  
  260.  
  261.  
  262.  
  263.  
  264.  
  265.  
  266.  
  267.  
  268.  
  269.  
  270.  
  271.  
  272.  
  273.  
  274.  
  275.  
  276.  
  277.  
  278.  
  279.  
  280.  
  281.  
  282.  
  283.  
  284.          PAGE1   Fascicle VI.7 - Rec. Q.709
  285.  
  286.                of large countries, and
  287.                -   40 minutes for 95 percent case of large countries.
  288.                Note 1 - Although the signalling component of the  international  switching
  289.          centre in the country was not included in Table 3/Q.709, it is  included  in  the
  290.          unavailability objectives.
  291.                Note 2 - The hypothetical signalling reference connection define  a  unique
  292.          path through the national and international networks, therefore when  considering
  293.          the overall unavailability of each national component, no account is taken of any
  294.          standby path, if provided, in that national network. The values given  are  based
  295.          on those for each component route-set as specified  in  Recommendation  Q.706,  S
  296.          1.1. They are provisional and for further study.
  297.                The maximum signalling transfer delay under normal conditions for  each  of
  298.          the national components of a connection should  not  be  worse  than  the  values
  299.          listed in Table 4/Q.709.
  300.                                                 TABLE 4/Q.709
  301.                             Maximum signalling delays for each national component
  302.                                                        Delay (Notes 1 and 2) (ms)
  303.                Country size         Percent of              Message type
  304.                                      connections   
  305.                                                        Simple         Processing 
  306.                                                     (e.g. answer)     intensive 
  307.                                                                        (e.g. IAM)
  308.                                         mean            390             600 
  309.          Large                                                      
  310.                                           95             520              800
  311.                                          mean            260              400 
  312.          Average-sized                                              
  313.                                           95             390              600
  314.               Note 1  - See Note to Table 2/Q.709.
  315.               Note 2 - The delay does not include any delay for the International 
  316.               Switching Centre in the country, which is included in the international 
  317.               component.
  318.  
  319.  
  320.  
  321.  
  322.  
  323.  
  324.  
  325.  
  326.  
  327.  
  328.  
  329.  
  330.  
  331.  
  332.  
  333.  
  334.  
  335.  
  336.  
  337.  
  338.  
  339.  
  340.  
  341.  
  342.  
  343.  
  344.  
  345.  
  346.  
  347.  
  348.  
  349.  
  350.  
  351.  
  352.  
  353.  
  354.  
  355.                                                         Fascicle VI.7 - Rec. Q.709   PAGE1
  356.  
  357.                4      Overall signalling delay for link-by-link signalling
  358.                From the hypothetical signalling reference connection  and  the  values  of
  359.          message transfer times given for signalling point and STP, the overall signalling
  360.          delay due to signalling point, and STP delays can be determined from Tables 2 and
  361.          4 of this Recommendation, for a given load in a given network. Average delays and
  362.          95 percentile delays are given in Table 5/Q.709 for various combinations of large
  363.          and average-sized countries. Average signalling point and STP  delays  at  normal
  364.          loading are assumed.
  365.                These values must be increased by the transmission propagation delays  (see
  366.          Table 1/Q.41).
  367.                                                 TABLE 5/Q.709
  368.                                       Maximum overall signalling delays
  369.                                                             Delay (Note) (ms)
  370.                Country size         Percent of              Message type
  371.                                      connections   
  372.                                                        Simple         Processing 
  373.                                                     (e.g. answer)     intensive 
  374.                                                                        (e.g. IAM)
  375.          Large                          mean            1170             1800
  376.          to                                                         
  377.          Large                            95             1450             2220
  378.          Large                           mean            1170             1800
  379.          to                                                         
  380.          Average-sized                    95             1450             2220
  381.          Average                        mean            1170             1800 
  382.          to                                                         
  383.          Average-sized                    95             1470             2240
  384.               Note - See Note to Table 2/Q.709.
  385.          5      Hypothetical signalling reference connection (HSRC) components 
  386.                for end-to-end signalling
  387.          5.1    General
  388.                The components  of  a  hypothetical  signalling  reference  connection  are
  389.          signalling end points (SEP), signalling points with SCCP relay function (SPR) and
  390.          STPs which are connected in  series  by  signalling  data  links  to  produce  an
  391.          end-to-end signalling connection (Note 1). The number of the  various  signalling
  392.          nodes depends on the size of the network. Two limits are prescribed to cover mean
  393.          or 95% cases. Separate cases are allowed for large  countries  and  average-sized
  394.          countries  (Note  2).  This  section  outlines  the  considerations  involved  in
  395.          formulating a hypothetical signalling reference connection and details the number
  396.          of hypothetical signalling reference connection components and  the  delays  they
  397.          produce.
  398.                Note 1 -  a)      Signalling End Point (SEP) - This includes processing in
  399.                          UP/AP (User part/application part), SCCP (Signalling  connection
  400.                          control  part),   MTP   (Message   transfer   part)   and   also
  401.                          MTP-SCCP-UP/AP
  402.                       b)  Signalling Point with SCCP relay function (SPR) - This includes
  403.                          only processing in MTP-SCCP-MTP
  404.                       c)  Signalling Transfer Point - This  includes  processing  in  MTP
  405.                          exclusively.
  406.                Note 2 - When the  maximum  distance  between  an  international  switching
  407.          centre and a subscriber who can be reached from it does not exceed  1000  km  or,
  408.          exceptionally, 1500 km, and when the country has less than n x  107  subscribers,
  409.          the country is considered as of average size. A country with  a  larger  distance
  410.          between an international switching centre and a subscriber, or with more than n x
  411.          107 subscribers is considered as of large size. (The value of n  is  for  further
  412.          study.)
  413.          5.1.1  Number of signalling nodes in the end-to-end HSRC
  414.  
  415.  
  416.  
  417.  
  418.  
  419.  
  420.  
  421.  
  422.  
  423.  
  424.  
  425.  
  426.          PAGE1   Fascicle VI.7 - Rec. Q.709
  427.  
  428.                 The  same  signalling  network  is  used  for   end-to-end   messages   and
  429.           link-by-link messages. This means that the maximum number of signalling nodes  is
  430.           equal in both cases. The maximum number of signalling nodes from the  originating
  431.           node to the destination node is 18 in 50 percent of the connections and 23 in  95
  432.           percent of the connections except for average-sized to average-sized country.  In
  433.           that case the value is 24.
  434.                 In general a fast transfer of end-to-end  signalling  messages  has  to  be
  435.           required. For such messages a route with a minimum number of signalling  transfer
  436.           and relay points is highly desirable.
  437.                 It is desirable to use the message routing of the MTP  (STP  functions)  as
  438.           far as possible and trying in this way to avoid processing in higher layers (SCCP
  439.           or user functions).
  440.           5.1.2  Signalling network availability
  441.                 The availability  of  a  signalling  connection  is  an  important  network
  442.           parameter. It is necessary for the availability to be significantly  better  than
  443.           the availability of the component being controlled (e.g. a circuit). A figure  of
  444.           ten minutes down time per year maximum  unavailability  is  recommended  for  any
  445.           particular signalling route set (Recommendation Q.706, S 1.1).
  446.                 This corresponds to an availability of 0.99998, which can  be  achieved  by
  447.           the use of suitable network redundancies.
  448.           5.1.3  Signalling message transfer delay
  449.                 Signalling message transfer delay is another important  network  parameter.
  450.           It affects call set up delay and also affects network response  time  to  service
  451.           requests made during a call.
  452.                 The use of signalling points with SCCP  relay  functions  (SPR)  should  be
  453.           kept to a minimum. In an SPR additional processing is performed which  causes  an
  454.           additional delay, for example address translation for CR  or  UDT  message  types
  455.           (processing intensive messages) or a local reference message mapping for CC or DT
  456.           messages (processing simple message types). The cross office transit time for SPR
  457.           is defined in Q.716. The cross-office transit time for an SEP is equal to Tcu  in
  458.           Q.766 or Q.725 and for an STP is equal to Tcs in Q.706.
  459.           5.2    International component of hypothetical signalling reference connection
  460.                 The  international  component  of  the  hypothetical  signalling  reference
  461.           connection includes all international signalling nodes (e.g. SPR and STP) in  the
  462.           connection. The maximum number of SPRs and  STPs  allowed  are  listed  in  Table
  463.           6/Q.709.
  464.                                                  TABLE 6/Q.709
  465.                           Maximum number of SPRs and STPs in international component
  466.                  Country size          Percent of      Number of       Number of 
  467.                                         connections        STPs            SPRs
  468.           Large                            mean             4              2
  469.           to                                                           
  470.           Large                              95              4              3
  471.           Large                             mean             6              2
  472.           to                                                           
  473.           Average-sized                      95              6              3
  474.           Average-sized                    mean             8              2
  475.           to                                                           
  476.           Average-sized                      95              8              4
  477.                 The  unavailability  of  the  overall  international   component   of   the
  478.           signalling network should not exceed the following totals per year for  both  the
  479.           50 and 95 percent cases:
  480.                  -   20 minutes for large country to large country;
  481.                  -   30 minutes for large country to average-sized country, and
  482.                  -   40 minutes per year for average-sized country to average-sized country.
  483.                 The maximum delay at the signalling nodes under normal conditions  for  the
  484.           international component of a connection should  not  be  worse  than  the  values
  485.           listed in Table 7/Q.709.
  486.                                                  TABLE 7/Q.709
  487.                        Maximum delay at the signalling nodes for international component
  488.                                                                 Delay (ms)
  489.                 Country size         Percent of              Message type
  490.                                       connections   
  491.  
  492.  
  493.  
  494.  
  495.  
  496.  
  497.                                                          Fascicle VI.7 - Rec. Q.709   PAGE1
  498.  
  499.                                                       Processing       Processing 
  500.                                                         simple         intensive 
  501.           Large                          mean            300              440
  502.           to                                                         
  503.           Large                            95             410              620
  504.           Large                           mean            340              480
  505.           to                                                         
  506.           Average-sized                    95             450              660
  507.           Average-sized                  mean            380              520
  508.           to                                                         
  509.           Average-sized                    95             600              880
  510.                 Note 1 - The maximum signalling nodes delay is the sum of all cross-office 
  511.                 delays involved.
  512.                 Note 2 - All values are provisional.
  513.           5.3    National components of hypothetical signalling reference connections
  514.                 The  national  components  of   the   hypothetical   signalling   reference
  515.           connection includes all national signalling nodes (e.g., SEP, SPR,  STP)  in  the
  516.           connection (but does not  include  the  international  switching  centre  in  the
  517.           country). The maximum number of SEPs, SPRs and STPs allowed are listed  in  Table
  518.           8/Q.709.
  519.                 The unavailability of each  of  the  overall  national  components  of  the
  520.           signalling network should not exceed the following totals per year:
  521.                  -   20 minutes for mean case of average-sized countries;
  522.                  -   30 minutes for 95 percent case of average-sized countries and mean case 
  523.                      of large countries, and
  524.                  -   40 minutes for 95 percent case of large countries.
  525.                                                  TABLE 8/Q.709
  526.                           Maximum number of SEPs, SPRs and STPs in national component
  527.               Country size      Percent of      Number of       Number pf       Number of 
  528.                                 connections        STPs            SPRs            SEPs
  529.                                    mean             4              1              1
  530.           Large                                                                
  531.                                      95              5              2              1
  532.                                
  533.  
  534.  
  535.  
  536.  
  537.  
  538.  
  539.  
  540.  
  541.  
  542.  
  543.  
  544.  
  545.  
  546.  
  547.  
  548.  
  549.  
  550.  
  551.  
  552.  
  553.  
  554.  
  555.  
  556.  
  557.  
  558.  
  559.  
  560.  
  561.  
  562.  
  563.  
  564.  
  565.  
  566.  
  567.  
  568.           PAGE1   Fascicle VI.7 - Rec. Q.709
  569.  
  570.           Average-sized             mean             2              1              1
  571.                                                                                
  572.                                      95              4              1              1
  573.                 Note 1 - Although the signalling component of the  international  switching
  574.           centre in the country is not included in Table 8/Q.709, it  is  included  in  the
  575.           unavailability objectives.
  576.                 Note 2 - The hypothetical signalling reference connection defines a  unique
  577.           path through the national and international networks, therefore when  considering
  578.           the overall unavailability of each national component, no account is taken of any
  579.           standby path, if provided, in that national network. The values given  are  based
  580.           on those for each component route-set as specified  in  Recommendation  Q.706,  S
  581.           1.1.
  582.                 The maximum delay at the signalling nodes under normal conditions for  each
  583.           of the national components of a connection should not be worse  than  the  values
  584.           listed in Table 9/Q.709.
  585.                                                  TABLE 9/Q.709
  586.                        Maximum delay at the signalling nodes for each national component
  587.                                                                 Delay (ms)
  588.                 Country size         Percent of              Message type
  589.                                       connections   
  590.                                                       Processing       Processing 
  591.                                                         simple         intensive 
  592.                                          mean            300              440
  593.           Large                                                      
  594.                                            95             430              640
  595.                                           mean            260              400
  596.           Average-sized                                              
  597.                                            95             300              440
  598.                  Note 1 - The maximum signalling nodes delay is the sum of all cross-office delays 
  599.                  involved.
  600.                  Note 2 - All values are provisional.
  601.           6      Overall signalling delay for end-to-end signalling
  602.                 The  link-by-link  signalling  delay  is  applicable  where  messages   are
  603.           processed by each signalling point (e.g. during call establishment). The  use  of
  604.           end-to-end signalling intended to reduce the overall signalling delay.
  605.                 From the hypothetical signalling reference connection  and  the  values  of
  606.           message transfer times given for SEPs, SPRs  and  STPs,  the  overall  signalling
  607.           delay due to the node delays can be determined  from  Tables  7  and  9  of  this
  608.           Recommendation, for a given load in  a  given  network.  Average  delays  and  95
  609.           percentile delays are given in Table 10/Q.709 for various combinations  of  large
  610.           and average-sized countries. Average signalling node delays at normal loading are
  611.           assumed.
  612.  
  613.                                                 TABLE 10/Q.709
  614.                                  Maximum overall delay at the signalling nodes
  615.                                                                 Delay (ms)
  616.                 Country size        
  617.  
  618.  
  619.  
  620.  
  621.  
  622.  
  623.  
  624.  
  625.  
  626.  
  627.  
  628.  
  629.  
  630.  
  631.  
  632.  
  633.  
  634.  
  635.  
  636.  
  637.  
  638.  
  639.                                                          Fascicle VI.7 - Rec. Q.709   PAGE1
  640.  
  641.                                      Percent of              Message type
  642.                                      connections   
  643.                                                      Processing       Processing 
  644.                                                        simple         intensive 
  645.          Large                          mean            900             1320
  646.          to                                                         
  647.          Large                            95             1270             1900
  648.          Large                           mean            900             1320
  649.          to                                                         
  650.          Average-sized                    95             1180             1740
  651.          Average-sized                  mean            9000             1320
  652.          to                                                         
  653.          Average-sized                    95             1200             1760
  654.               Note 1 - The maximum signalling nodes delay is the sum of all cross-office delays 
  655.               involved.
  656.               Note 2 - All values are provisional.
  657.          7      Remarks
  658.          7.1     The  above  values  for  signalling  delays  assumes  a  message   length
  659.          distribution as given in Table 2/Q.706 and Table 2/Q.725,  with  a  mean  message
  660.          length of 15 octets. However, a message length of e.g. 128 octets for  SCCP  user
  661.          data in CR and CC messages and 255 octets for SCCP user data in DT  messages  are
  662.          permissible. For such a message length the transmission time at 64 kbit/s is,  in
  663.          each signalling node, about 15 ms (128 octets) to 30 ms (255 octets) longer.
  664.          7.2    When defining an overall signalling delay the propagation  delay  must  be
  665.          included. This delay cannot be completely neglected due to the geographical  size
  666.          of the HSRC (see Table 1/Q.41).
  667.  
  668.  
  669.  
  670.  
  671.  
  672.  
  673.  
  674.  
  675.  
  676.  
  677.  
  678.  
  679.  
  680.  
  681.  
  682.  
  683.  
  684.  
  685.  
  686.  
  687.  
  688.  
  689.  
  690.  
  691.  
  692.  
  693.  
  694.  
  695.  
  696.  
  697.  
  698.  
  699.  
  700.  
  701.  
  702.  
  703.  
  704.  
  705.  
  706.  
  707.  
  708.  
  709.  
  710.          PAGE1   Fascicle VI.7 - Rec. Q.709
  711.  
  712.