  1.      LOW INVESTMENT PROPAGATION/WINTER PROTECTION STRUCTURE
  2.             T.E. Bilderback, R.E. Bir and M.A. Powell
  3.               Horticultural Extension Specialists 
  4.           September 1993 (Revised)      LEAFLET NO. 404
  5.  
  6.  
  7. Basic Structure:
  8.      Quonset Design
  9.           3' High x 6' Wide x 20' Long
  10.           3/4" schedule 40 PVC pipe bows slipped into 3/4"
  11.                electrical conduit hangers
  12.           6 ml white copolymer cover
  13.           2" x 8" treated lumber kickboards along sides and ends
  14.  
  15.  
  16. List of Structural Materials and Approximate Costs (1993):
  17.  
  18.       Quantity               Description                    Cost 
  19.  
  20.           4         3/4" PVC pipe, 20' lengths             $10.40
  21.           1         12' x 30' white copolymer film, 6 mil   12.60
  22.           32        3/4" electrical conduit hangers          6.08
  23.           1         2" x 8" x 12' treated lumber            10.96
  24.           4         2" x 8" x 10' treated lumber            36.52
  25.           1 lb      16 penny common nails                    0.87
  26.           1         200 ft. roll guage steel wire            4.38
  27.           1 lb      roofing nails                             .87
  28.           4         metal 4"x5" mending plates (4 x4.5)      1.80
  29.                                                 Total       84.48
  30.  
  31.  
  32. Tools Required for Construction:
  33.  
  34.      Carpenter saw                          Garden rake
  35.      Carpenter hammer                       Side cutting pliers
  36.      Folding rule or tape measure           Sharp pocket knife
  37.      Round pointed shovel                   Builder's square
  38.      Pencil
  39.  
  40.  
  41. Site Selection:  Choose a site for your structure that is fairly
  42. level and preferably has some shade.  If the structure is to be
  43. used exclusively for propagation, it should be oriented east-
  44. west.  If its primary use will be in providing winter protection
  45. for nursery crops, it should be oriented north-south.  There
  46. should be a water source nearby since water is needed for both
  47. propagation and winter protection.
  48.  
  49.  
  50. Construction:
  51.  
  52.       1.     Level an area (properly oriented depending upon
  53.              whether your structure will be used for propagation 
  54.              or winter protection) 8' wide x 24' long.
  55.  
  56.       2.     Square ends of lumber.
  57.  
  58.       3.     Cut the 2" x 8" x 12' in half so that you have two  
  59.              (2) pieces 2" x 8" x 6'.  These 6' sections will    
  60.              be used for the ends of the bed.
  61.  
  62.       4.     Butt the ends of two (2) of the 2" x 8" x 10's
  63.              together and nail securely so that you have a 2" x  
  64.              8" x 20' using splice connectors on each side of the
  65.              splice.
  66.  
  67.       5.     Repeat Step 4 using the remaining two (2) 2" x 8" x
  68.              10's.  The two (2) bed sides (kickboards) are now
  69.              assembled.
  70.  
  71.       6.     Lay kickboard sides on edge 6' apart on the levelled
  72.              area and place 2" x 8" x 6' section outside each    
  73.              end.  Be certain that corners are square, then nail 
  74.              together securely.  You now have a rectangular box  
  75.              with open top and bottom that has inside dimensions 
  76.              of 5'8 3/4" x 20'.
  77.  
  78.       7.     At each of the four (4) corners along the length of
  79.              the structure (on the inside edge) nail in a conduit
  80.              connector so that the top of the connector is flush
  81.              with the top edge of the 2" x 8".  Any nails which  
  82.              come through should be bent over so that they will  
  83.              not tear the copolymer cover.
  84.  
  85.       8.     Repeat Step 7 but with the bottom of the connector
  86.              flush with the bottom of the 2" x 8".
  87.  
  88.       9.     Starting from the center of either of the top end
  89.              conduit hangers mark off the kickboards along the
  90.              length of the structure at 33 13/16 inch intervals.
  91.  
  92.      10.     At each of the marked intervals nail in two (2)
  93.              conduit hangers as in Steps 7 and 8.
  94.  
  95.      11.     Cut the four (4) 20' lengths of PVC pipe in half so
  96.              that you have eight (8) 10' pieces.
  97.  
  98.      12.     For each section of PVC pipe, slip one end down
  99.              through a set of conduit hangers, bend the pipe in a
  100.              bow across the width of the structure and slip the
  101.              other end of the pipe down through the opposite set 
  102.              of conduit hangers.
  103.  
  104.      13.     Install remaining 3/4" PVC bows as in Step 12.
  105.  
  106.      14a.    If the structure is going to be used for winter
  107.              protection of containerized plants follow Steps 15  
  108.              and 16, then Steps 19-22.
  109.  
  110.      14b.    If the structure is going to be used for propagation
  111.  
  112.              of cuttings follow Steps 17 and 18, then Steps      
  113.              19-22.
  114.  
  115.      15.     Place containerized materials inside the structure. 
  116.              More cold tolerant plants such as creeping junipers
  117.              should be placed around the perimeter.
  118.  
  119.      16.     Water all containers thoroughly, then follow Steps  
  120.              19-22.  Preemergent herbicides should have been     
  121.              applied 1 month earlier.  Apply fungicides after    
  122.              irrigation.  Rodent bait should be applied just     
  123.              before covering.
  124.  
  125.      17.     Fill the structure to a depth of 6" of 7" with      
  126.              clean, moist propagating medium.  Be certain that   
  127.              medium is level.  An alternative to filling the     
  128.              frame is use of cellular trays.
  129.  
  130.      18.     Insert cuttings and water in thoroughly; then follow
  131.              Steps 19-22.
  132.  
  133.      19.     Using flexible wire or heavy cord tie the bows
  134.              together so that they cannot flex to either side. 
  135.              Another alternative is to use a single PVC 20"      
  136.              length centered at the top and attached to each bow 
  137.              to add greater rigidity to the frame.
  138.  
  139.      20.     Center the 12' x 30' sheet of white copolymer film
  140.              over the hoop frame
  141.  
  142.      21.     The cover can be secured by covering the 1' of      
  143.              surplus film along one of the long sides with soil. 
  144.              To allow easy access to the plants or cuttings the  
  145.              other three sides of the film can be held down with 
  146.              boards, rocks or pieces of wood.  Winter protection 
  147.              structures should have kickboards braced with soil  
  148.              or gravel during snow season to provide extra       
  149.              support. 
  150.  
  151.      22.     On warm days your structure may require venting.    
  152.              This can be done by opening the ends and then       
  153.              closing them down again later in the day.
  154.                                         
  155.  
  156. If properly constructed the framework of your quonset should last
  157. for years.  With a minimum amount of care the white copolymer
  158. cover should last for two (2) years.  Precautions should be taken
  159. to insure that nails and wire used in construction of the
  160. framework are properly bent and do not tear the cover.  Also, if
  161. the structure is not going to be used for prolonged periods, it
  162. is best to remove the white copolymer cover, carefully roll it up
  163. and store it out of direct sunlight.  Do not fold the cover as
  164. the creases will cause weak areas which will tear easily when the
  165. cover is replaced on the quonset!  Storage of the cover, when not