Delivery of Part One
Revision A - 28 MARCH 1996
|
| Name | Position | E-mail address |
---|
Author(s): | Martin Fredriksson | Delivery Manager | pt93mf@sikt.hk-r.se |
Responsible: | Martin Fredriksson | Delivery Manager | pt93mf@sikt.hk-r.se |
To: | The Saida Project | | |
Cc: | | | |
1 Preparations
1.1 Files to Deliver
General File Properties
It must be verified that all files (executables, source code, manuals and other documents)...
- ...have the supposed access mode.
- ...have the supposed version.
- ...have the supposed copyright notices.
The verification shall be done according to the User Manual (see [SAIDA 96-2] and [SAIDA 96-3]).
Documents
The following documents must be created:
- Installation manual.
The Delivery Manager is responsible for this document.
- User manual.
The individual development teams are responsible for this document.
- Solution decision document.
The individual development teams are responsible for this document.
- Feature description document.
The individual development teams are responsible for this document.
- Delivery approval document (i.e. Test Specification - see [SAIDA 96-4] and [SAIDA 96-5]).
The individual development teams are responsible for this document.
1.2 Backups and Copies
Master Backup
Delivery Copies
1.3 Installation Script
To prevent the occurance of human errors when installing the software to be delivered, only a simple script shall be run to make the full installation.
2 Delivery
2.1 Installation
Location
- Available via FTP and installed on the EnerSearch PC at SIKT.
Format
3 Installation
3.1 Verifying Completeness
Files
- Verify that all the required files were installed according to the User Manual (see [SAIDA 96-2] and [SAIDA 96-3]).
3.2 Verifying Correctness
Files
It must be verified that the files...
- ...have the supposed access mode.
3.3 Validation
According to Contract
- Validation of the delivery shall be made according to contract.
3.4 Approval
Verification
- Verify delivery against the defined Test Specification (see [SAIDA 96-4] and [SAIDA 96-5]).
4 Appendix
4.1 Estimations
Estimations
Activity | ID | Est. Time | Est. Basis | Start | End | Dep |
---|
Files to Deliver | 3.1.1 | | | | | |
Access Mode | 3.1.1.1 | 0.5 | 1 pers. * 0.5 hour | 1996-04-09 | 1996-04-09 | 3.1.1.4 3.1.1.5 3.1.1.6 3.1.1.7 |
Version | 3.1.1.2 | 0.5 | 1 pers. * 0.5 hour | 1996-04-09 | 1996-04-09 | 3.1.1.1 |
Copyright | 3.1.1.3 | 0.5 | 1 pers. * 0.5 hour | 1996-04-09 | 1996-04-09 | 3.1.1.2 |
Installation Manual | 3.1.1.4 | 3 | 1 pers. * 3 hours | 1996-04-04 | 1996-04-04 | 3.1.1.5 3.1.1.6 3.1.1.7 |
User Manual | 3.1.1.5 | 0 | Done by the individual Development Teams | 1996-04-04 | 1996-04-04 | |
Solutions & Features | 3.1.1.6 | 4 | 1 pers. * 4 hours | 1996-04-04 | 1996-04-04 | |
Delivery Approval | 3.1.1.7 | 0 | Done by the individual Development Teams | 1996-04-04 | 1996-04-04 | |
Backups and Copies | 3.1.2 | | | | | 3.1.1 |
Compilation of Master Backup | 3.1.2.1 | 0.5 | Configuration Manager * 0.5 | 1996-04-09 | 1996-04-09 | |
Compilation of Delivery Copies | 3.1.2.2 | 0.5 | Configuration Manager * 0.5 | 1996-04-09 | 1996-04-09 | |
Installation Script | 3.1.3 | | | | | 3.1.2 |
Script | 3.1.3.1 | 4 | Support Manager * 4 hours | 1996-04-09 | 1996-04-09 | |
Installation | 3.1.4 | | | | | 3.1.3 |
Location | 3.1.4.1 | 0.5 | Support manager * 0.5 hours | 1996-04-10 | 1996-04-10 | |
Verifying Completeness | 3.1.5 | | | | | 3.1.4 |
Files | 3.1.5.1 | 0.5 | Support Manager * 0.5 hours | 1996-04-10 | 1996-04-10 | |
Verifying Correctness | 3.1.6 | | | | | 3.1.5 |
Access Mode | 3.1.6.1 | 0.5 | Support Manager * 0.5 hours | 1996-04-10 | 1996-04-10 | |
Validation | 3.1.7 | | | | | 3.1.6 |
According to Contract | 3.1.7.1 | 0.5 | Project Manager * 0.5 hours | 1996-04-10 | 1996-04-10 | |
Approval | 3.1.8 | | | | | 3.1.7 |
Verification | 3.1.8.1 | 8 | 2 pers. * 4 hours | 1996-04-11 | 1996-04-11 | |
Total | | 23.5 | | | | |
These are the estimations for delivery of part one of the Saida project. The basis for the individual dates are specified in [SAIDA 96-6] and the basis for the estimations are created on a totally personal level.
4.2 References
[SAIDA 96-1] Thuresson, M., "Configuration Plan" - University of Karlskrona/Ronneby, 1996.
[SAIDA 96-2] SIW Development Team, "WWW Interface - User Manual" - University of Karlskrona/Ronneby, 1996.
[SAIDA 96-3] SAGA Development Team, "Data Server - User Manual" - University of Karlskrona/Ronneby, 1996.
[SAIDA 96-4] SIW Development Team, "WWW Interface - Test Specification" - University of Karlskrona/Ronneby, 1996.
[SAIDA 96-5] SAGA Development Team, "Data Server - Test Specification" - University of Karlskrona/Ronneby, 1996.
[SAIDA 96-6] The SAIDA Project, "Contract" - University of Karlskrona/Ronneby, 1996.
- Delivery of Part One
-
- 1 - Preparations
-
- 1.1 - Files to Deliver
-
- General File Properties
-
- Documents
-
- 1.2 - Backups and Copies
-
- Master Backup
-
- Delivery Copies
-
- 1.3 - Installation Script
-
- 2 - Delivery
-
- 2.1 - Installation
-
- Location
-
- Format
-
- 3 - Installation
-
- 3.1 - Verifying Completeness
-
- Files
-
- 3.2 - Verifying Correctness
-
- Files
-
- 3.3 - Validation
-
- According to Contract
-
- 3.4 - Approval
-
- Verification
-
- 4 - Appendix
-
- 4.1 - Estimations
-
- 4.2 - References
-