Delivery of Part One

Revision A - 28 MARCH 1996

 NamePositionE-mail address
Author(s):Martin FredrikssonDelivery Managerpt93mf@sikt.hk-r.se
Responsible:Martin FredrikssonDelivery Managerpt93mf@sikt.hk-r.se
To:The Saida Project  
Cc:   

1 Preparations

1.1 Files to Deliver

General File Properties
It must be verified that all files (executables, source code, manuals and other documents)...

The verification shall be done according to the User Manual (see [SAIDA 96-2] and [SAIDA 96-3]).

Documents
The following documents must be created:

1.2 Backups and Copies

Master Backup
Delivery Copies

1.3 Installation Script

To prevent the occurance of human errors when installing the software to be delivered, only a simple script shall be run to make the full installation.

2 Delivery

2.1 Installation

Location
Format

3 Installation

3.1 Verifying Completeness

Files

3.2 Verifying Correctness

Files
It must be verified that the files...

3.3 Validation

According to Contract

3.4 Approval

Verification

4 Appendix

4.1 Estimations
Estimations
ActivityIDEst. TimeEst. BasisStartEndDep
Files to Deliver3.1.1     
Access Mode3.1.1.10.51 pers. * 0.5 hour1996-04-091996-04-093.1.1.4

3.1.1.5

3.1.1.6

3.1.1.7

Version3.1.1.20.51 pers. * 0.5 hour1996-04-091996-04-093.1.1.1
Copyright3.1.1.30.51 pers. * 0.5 hour1996-04-091996-04-093.1.1.2
Installation Manual3.1.1.431 pers. * 3 hours1996-04-041996-04-043.1.1.5

3.1.1.6

3.1.1.7

User Manual3.1.1.50Done by the individual Development Teams1996-04-041996-04-04 
Solutions & Features3.1.1.641 pers. * 4 hours1996-04-041996-04-04 
Delivery Approval3.1.1.70Done by the individual Development Teams1996-04-041996-04-04 
Backups and Copies3.1.2    3.1.1
Compilation of Master Backup3.1.2.10.5Configuration Manager * 0.51996-04-091996-04-09 
Compilation of Delivery Copies3.1.2.20.5Configuration Manager * 0.51996-04-091996-04-09 
Installation Script3.1.3    3.1.2
Script3.1.3.14Support Manager * 4 hours1996-04-091996-04-09 
Installation3.1.4    3.1.3
Location3.1.4.10.5Support manager * 0.5 hours1996-04-101996-04-10 
Verifying Completeness3.1.5    3.1.4
Files3.1.5.10.5Support Manager * 0.5 hours1996-04-101996-04-10 
Verifying Correctness3.1.6    3.1.5
Access Mode3.1.6.10.5Support Manager * 0.5 hours1996-04-101996-04-10 
Validation3.1.7    3.1.6
According to Contract3.1.7.10.5Project Manager * 0.5 hours1996-04-101996-04-10 
Approval3.1.8    3.1.7
Verification3.1.8.182 pers. * 4 hours1996-04-111996-04-11 
Total 23.5    

These are the estimations for delivery of part one of the Saida project. The basis for the individual dates are specified in [SAIDA 96-6] and the basis for the estimations are created on a totally personal level.

4.2 References

[SAIDA 96-1] Thuresson, M., "Configuration Plan" - University of Karlskrona/Ronneby, 1996.

[SAIDA 96-2] SIW Development Team, "WWW Interface - User Manual" - University of Karlskrona/Ronneby, 1996.

[SAIDA 96-3] SAGA Development Team, "Data Server - User Manual" - University of Karlskrona/Ronneby, 1996.

[SAIDA 96-4] SIW Development Team, "WWW Interface - Test Specification" - University of Karlskrona/Ronneby, 1996.

[SAIDA 96-5] SAGA Development Team, "Data Server - Test Specification" - University of Karlskrona/Ronneby, 1996.

[SAIDA 96-6] The SAIDA Project, "Contract" - University of Karlskrona/Ronneby, 1996.


Delivery of Part One
1 - Preparations
1.1 - Files to Deliver
General File Properties
Documents
1.2 - Backups and Copies
Master Backup
Delivery Copies
1.3 - Installation Script
2 - Delivery
2.1 - Installation
Location
Format
3 - Installation
3.1 - Verifying Completeness
Files
3.2 - Verifying Correctness
Files
3.3 - Validation
According to Contract
3.4 - Approval
Verification
4 - Appendix
4.1 - Estimations
4.2 - References