(Contents)(Previous)(Next)

Project Task Details Page

Purpose

This page lets you specify the associated project task's details.

Usage

Option Description
Description The project task's name or description
Priority The priority that you attribute to this task. You may choose from five different priority levels. The descriptions associated with each level are definable from within Supervisor mode.
Has Deadline Check this check box if you wish to specify a deadline by which this task must be completed.
Deadline Enter the date and time of the task's deadline.
Milestone Check this check box to indicate that this project task represents a milestone.
Planned Check this check box to plan the project task.
Planned Start The planned start date and time for the project task
Planned End The planned end date and time for the project task
Planned Duration The planned duration for the project task
Complete Check this check box to indicate that this task has been completed or specify a percentage complete in the adjacent field.


Next