Taco Information
Entering EVO#3
EVO#3
- CDR converter
- File receiver
- Optimizations
- Testing (How much are we capable of processing
- Handle the comments that Europolitan gave us, i.e the changes in the database design
- User documentation
- QMG rework of the old quality documents.
Committments
- What about receiving CDR files via FTP? (req. F332) Esping
- What about the unknown CDR's, i.e roaming calls? (req. F336) Esping
- Responsible for the optimizations, see to that there will be better performance Esping,Dan Andersson, 20 May, Monday, 08.15, start
- Take care of the rewrite of the requirements specification and the contract Young, 20 May Monday 08.15 (start)
- Responsible for the FileReceiver Esping, 20 May, Monday, 08.15, ready and working
- Responsible for the CDR converter Dan Andersson, 20 May, Monday, 08.15, ready and working
- User documentation ready, Marcus Helgesson, finnished, 22 May, , afternoon
- Test specification ready, Marcus Helgesson, finnished, 17 May, Friday, afternoon
- The intermediate code has to be documented, Wigge, 22 May Wednesday, written and ready to print
- Make a specification of what's to be included in the last delivery, included an attribute spec., Tobias Eriksson, May 15, Wednesday, 08.15
- Make a WBS/top level design specification, Tobias Eriksson, May 15, Wednesday, 08.15
- Make a subrequirements specification, Tobias Eriksson, May 20, Monday, 16.00, ready
- Check the changes made to the Database design.
- Fill in the tags for the requirements in the design documents, concerns everybody.
- Testdata has to be made, this includes all areas, i.e CDR's, CDR-mapping file, Intermediate code etc. Responsibles are Dan Andersson CDR-Mapping, Esping CDR's, Wigge 4G HCL.
General Information
- Information about number analysis, resp. Young, document describing this
- Survey about Threads, which we decided not to use, see ..., Wigge
- CDR information can be found here -> , Esping, 26 April ready and working
General schedule (this is a preliminary schedule)
Week 21
Monday Implementation and filuring kring optimeringar
Tuesday Implementation finnished, Optimizations
Wednesday Optimizations and Final Integration
Thursday Testing
Friday Final Delivery
Saturday
Sunday