FLIGHT NO: 2-51-92 DATE OF REPORT: May 23, 1967
PILOT: Maj. W. Knight DATE OF FLIGHT: May 8, 1967
CARRIER AIRCRAFT: B-52 #008 LAUNCH LAKE: Hidden Hills
ENGINE: S/N 109 APU #1 21 AN APU #2 22AN
PURPOSE OF FLIGHT: (1) Stability and Control with Dummy Ramjet
(2) Canopy Eyelid Checkout
(3) T/C System Checkout
(4) Ramjet Local Flow Data
(5) Alternate Airspeed Source Evaluation
I. Discussion of Previous Operations
Reliable recording of the T/C's was not obtained, and it was then decided to move the entire T/C package to the environmentally controlled instrument bay. (Space for this relocation was available since the Startracker experiment has been terminated,)
B. Nose gear "thin" door installation.
C. L/H windshield eyelid installation.
D. Yaw ASAS installation.
E. Installation of an instrumented dummy Ramjet and associated ventral stub "pylon" modification.
F. Removal of BCS rockets and valves to save weight.
G. Removal of Startracker experiment and deactivation of "flip-top" doors.
H. A screen was installed over each transformer/rectifier case opening to keep stray hardware from causing short circuits.
I. Installation of ARC-51 radio.
B. A captive flight (2-C-90) was made on December 22,
1966, to check the operation of the T/C heater modification under the severe
chilled environment of captive flight, (see Section I-A). Secondary objectives
were:
2. Checkout of an alternate procedure for ground erection of the inertial system (inertial mode throughout the flight.)
3. Functional check of the "TAZ 8" ball nose.
C. The X-15 was placed in work status following the captive flight. The modifications made during this time are listed in Section II.
D. During the week of January 30, 1967, the X-15 was used in a demonstration of ablative particle contamination control by the Martin Company, using the newly constructed ablative spray facility at FRC. The demonstration was successful.
E. In Mid-March, the first dummy Ramjet was received from NAA. Installation of instrumentation was begun. This was followed by fit checks and a resonant vibration test with the Ramjet installed on the X-15.
F. Preflights were without incident. Engine and APU ground runs were completed on April 27, 1967.
G. The first attempt at Flight 2-51-91 was canceled on 5/1/67 due to unavailability of the C-130 support aircraft, and the X-15 was demated to permit the B-52 to be used for an M-2 flight. The M-2 flight was made on Tuesday, 5/2 and the X-15 remated that same evening. An incorrectly grounded Yaw servo caused Yaw SAS channel failures on two successive days (5/3 and 5/4).
H. Adverse weather caused a pre-launch abort (2-A-91) on Friday, 5/5/67.
The inertial velocity meter indicated low throughout the flight. A computer error is suspected.
ARC-51 radio reception by the X-15 pilot was intermittent
at times. Some trouble-shooting is necessary in this system.
Perry V. Row William P. Albrecht
X-15 Senior Project Engineer X-15 Project Engineer