FLIGHT NO: 2-45-81 DATE OF REPORT: July 5, 1966
PILOT: L/Col Rushworth DATE OF FLIGHT: July 1, 1966
CARRIER AIRCRAFT: B-52 #008 LAUNCH LAKE: Mud Lake
ENGINE: S/N 106 APU #1 25 AN APU #2 22AN
PURPOSE OF FLIGHT: (1) External Tank Operation and Separation:
(2) Handling Characteristics with External Tanks
(3) Local Flow Data for Ramjet
(4) Martin Ablative Tests
I. Discussion of Previous Operations
2. The drogue-chute release delay time was increased to maintain stability during main chute deployment.
3. Sleeves were added to the main chute nose-cone separator device to prevent loss of gas pressure from the separator. (Reason for failure of main chute to deploy from Lox tank on Flight 2-43-75).
4. The riser length for the drogue chute was increased to improve stability.
5. An FM TM system was installed in the Lox tank to transmit data on tank accelerations and rotational rates during separation.
6. Modified "thin" Teflon lip seals with Mylar back-up
seal were added to the Lox drop tank feed line in place of the heavy gage
lip seal originally provided.
C. Cut RH engine firewall panel in two sections to facilitate installation.
D. Added third tank eject button-switch for "partial" full ejection of tanks.
B. Failure of S-29 switch in the engine control box during a hangar functional test forced replacement of the engine control box and the engine was rerun on June 22.
C. Captive Flight 2-C-80 was completed on Monday, June 27. Purpose of this captive was to rehearse for the drop flight and checkout the functioning of the external drop tank feed system. The feed system worked very well, although the He flow T/M indication for the NH3 tank failed. The SAS Pitch/Roll damper also failed. A new RH Pitch/Roll servo was installed and several Pitch/Roll module components of the SAS case were replaced. However, during subsequent alignment the new servo exhibited instability (severe "jitter") and was again replaced. Realignment of SAS was satisfactory, but an ASAS case failure required replacement of that item. Final SAS/ASAS preflight was completed on Thursday, June 30. In an effort to insure proper NH3 He flow indication, the transducer was replaced and a parallel T/M channel was provided.
Perry V. Row William P. Albrecht
X-15 Senior Project Engineer X-15 Project Engineer